SARA_Information response

of 27

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Wednesday, 26 July 2023

Our Ref: 22070
Your Ref: 2210-31715 SRA


       DEPARTMENT OF STATE DEVELOPMENT, INFRASTRUCTURE,
       LOCAL GOVERNMENT AND PLANNING (SEQ-NORTH REGION)
       PO BOX 1129
       MAROOCHYDORE QLD 4558


       ATTENTION: Danika Cowie


Dear Danika


INFORMATION RESPONSE
OTHER CHANGE TO DEVELOPMENT APPROVAL

3 & 7 SERENITY CLOSE NOOSA HEADS QLD


Further to your information request for the abovementioned development application we now
respond to all of the information requested.

In support of the response please find attached:
• Amended Proposal Plans
• Amended Preliminary Earthworks Plan
• Amended Traffic Impact Assessment
• Ecological Assessment Report
• State Code 6 – PO26-PO31 Response (Appendix A)
• Legal advice on Other Change assessment criteria (Appendix B)


                              START INFORMATION RESPONSE

Public Passenger Transport

1. Action:
   Provide revised proposal plans and supporting traffic engineering information to demonstrate
   compliance with performance outcome (PO)26 – PO31 of State code 6: Protection of State
   transport networks (State code 6) of the SDAP. In particular, the following should be addressed:
   a) Demonstrate how bus turnaround will be able to be achieved at all times, given on-street car
       parking is allowed in the Serenity Close cul-de-sac. Advice is provided that unbroken yellow
       no stopping line may need to be considered.
Log in to download the original file

SARA_Information response.pdf · 7.4 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 26 pages

Page 2

   b) Demonstrate that the bus setdown facility will be provided in a 'front of house' location with
      respect to the resort complex reception and check-in lounge. Whilst bus/coach turnaround
      will likely need to be achieved via Serenity Close with a bus zone parallel to the loading dock,
      the actual bus setdown arrangement for passengers should be convenient, accessible and
      legible with respect to the resort complex customer entry. An indented bus zone (parallel to
      kerb) and adjacent pathway arrangement along Serenity Close could be considered, for
      instance, near the retail entry. The applicant should also consider potential options for bus
      setdown via Grant Street if that is capable of accommodating the maximum design vehicle
      swept path.

       A perpendicular bus zone is generally not recommended for passenger loading although the
       constraints of bus turnaround are acknowledged. All passenger loading and unloading,
       including from the front and back doors of a bus where a perpendicular arrangement is
       proposed should be on the site. The applicant should consider providing a longer bus zone
       on the site by altering the building layout to accommodate this if they can demonstrate that
       the bus setdown facility can only be provided of the Serenity Close cul-de-sac.

       The applicant may also like to potentially consider providing a designated mini-bus parking
       space in the passenger loading zone on Level 03, noting that the swept path of the passenger
       loading area will need to cater for a taxi catering for people with disabilities.

   c) Demonstrate that the bus setdown facility will include a covered passenger waiting area with
      seats and a safe boarding and alighting point.

   d) Demonstrate that a safe, direct and convenient pedestrian pathway will be provided between
      the bus setdown facility (boarding point and waiting area) and the resort complex lobby which
      is DDA compliant. This should minimise vehicular/pedestrian conflict with service vehicle
      docking arrangements and any other vehicles on the Serenity Close driveway.

Response:
Refer attached amended Proposal Plans and Traffic Impact Assessment. As discussed in section
2.2 of the Traffic Impact Assessment, the target market for the proposed hotel does not include tour
groups, as such coaches will not require access to the site or park within the site / surrounding
streets. The hotel will have a minibus service, with the Porte Cochere/ set down area designed to
cater for a 21 seater minibus. The minibus service will be used to transport guests from various
destinations, including transport hubs such as the Noosa Junction bus interchange. Included in
Appendix A is a code response to PO26 – PO31 of State code 6, demonstrating compliance with the
performance outcomes.

2. Action:
   Provide revised proposal plans and supporting traffic engineering information to demonstrate
   compliance with PO26 – PO31 of State code 6. In particular, the following should be addressed:
   a) Provide details of the proposed private ferry service and how this would be achieved. It is
      unclear as to whether the pathway from Serenity Close to the Settler's Cove ferry terminal is
      public or private.
   b) Provide details of how resort guests will be transferred to and from the ferry service and
      whether this will be via bus/mini-bus/coach or active transport. The pathway between
      Settler's Cove and Serenity Close is approximately 130m in length and there is an
      approximate 80m distance between the pathway and the proposed resort complex (back of
      house). It is likely passengers will need to be transported to the resort complex entry in Grant
      Street.

Page 3

   c) Demonstrate that adequate capacity will be provided in the bus setdown facility or passenger
      loading zone to cater for any regular bus or mini-bus services for a private ferry shuttle and
      that provision will be made on site for bus lay-by parking where the buses/minibuses are
      owned and operated by the resort. The passenger loading zone would need to be designed
      for the swept path of the maximum design vehicle likely to use it.
   d) Demonstrate that active transport infrastructure including safe, direct, convenient and
      inclusive pedestrian paths will be provided as part of the development and in the external
      road network to cater for any pedestrian and cyclist movements associated with the private
      ferry service.

Response:
The proposed ferry is an additional transport option being explored for the development and is not
intended to form part of the development approval. Details and confirmation of the proposed ferry
have not been finalised at this stage. Should more detailed investigations establish the ferry to be
viable, then it would operate as ancillary to the approved use. Compliance with PO26 – PO31 of
State code 6 is achieved, as demonstrated in the code response included in Appendix A, without the
ferry.

State code 25: Development in South East Queensland koala habitat areas (State code 25)

3. Action:
   Provide a response to the latest version of State code 25 in its entirety, identifying how the
   proposed development meets each PO.

Response:
Legal advice from planning law specialists Connor O’Meara has been obtained on the assessment
of a change application, which is not a minor change, and is included in Appendix B. This advice
confirms that:
(i)   Pursuant to Part 10 of Schedule 10 of Planning Regulation 2017 (“the Koala Regulations”)
      development is assessable development to the extent that it interferes with koala habitat in a
      koala habitat area that is not a koala priority area;
(ii) The Koala Regulations do not apply to the extent that the development (i.e. the interference
      with koala habitat) is consistent with the Development Approval; and
(iii) In their view, the interference with koala habitat proposed by the change application is
      consistent with the Development Approval and therefore the Koala Regulations are not
      engaged and do not apply.

The legal advice further confirms that even if the Koala Regulations were to apply, the assessment
according to law must be limited to the extent of the change and not upon elements of the
development approval that are not changing.

In addition refer attached Ecological Assessment Report and correspondence from Litoria
Consulting included in Appendix C. The Ecological Assessment Report demonstrates that the
proposed change application will result in a net gain in koala habitat through the additional retention
of areas containing ecological values.

Page 4

4. Action:
   Provide a copy of the development approvals and development plans that exist over the site.

Response:
A copy of the development approval and development plans that exist over the site are included in
Appendix 1 of the Ecological Assessment Report.

5. Action:
   To demonstrate compliance with State code 25, it is recommended a koala habitat values
   assessment, carried out by a suitably qualified ecologist, be undertaken to identify koala habitat
   areas, koala habitat and koala habitat values that exist on site. The results of this assessment
   should be provided with the application and should be used to guide the location, siting, design
   and phasing of the proposed development to demonstrate compliance with State code 25.

   The koala habitat values assessment should include a tree survey plan that identifies the location
   of all native trees on site along with:
   • identification numbers that correspond to each tree
   • GPS coordinates for each tree
   • the species of each tree
   • the height of each tree
   • the circumference of each tree at 1.3m above the ground
   • the tree protection zone of each tree
   • special features that exist on each tree (e.g., hollows (including approximate size), nests,
       scratches, termitaria, etc.)
   • what tree species utility it has been assigned by Appendix 4 of Spatial modelling for koalas
       in South East Queensland
   • if a tree is a koala habitat tree, whether it is a non-juvenile koala habitat tree (NJKHT)
   • whether each tree is inside or outside the mapped koala habitat area
   • whether each tree is to be retained or removed (noting that trees which could be removed by
       exempted development created as a natural and ordinary consequence of the development
       being approved (e.g. firebreaks, fire management lines, access tracks, fences) are
       considered trees to be removed)
   • identifies the number of non-juvenile koala habitat trees proposed to be removed located in
       mapped koala habitat areas.

Response:
Notwithstanding the proposed change is consistent with the development approval, an assessment
of Koala habitat values, including a Koala survey has been undertaken and detailed in the attached
Ecological Assessment Report.

As detailed in this report a targeted Koala survey was conducted over the entire site by OWAD
Environment on 20 April 2023 with a team of ecologists and a purpose-bred detection dog certified
by the Australian Canine Detection Certification Council for Koala and Quoll scat determination. In
addition any evidence of Koala usage (scat, sighting and Koala scratches) was also recorded during
a detailed tree survey and botanical survey, with over 100 hours spent on site between May 2022
and April 2023 by 4 qualified ecologists. This report and survey confirms that the site does not
currently form part of the home range of any individual Koala, nor has it been recently used by
Koalas. Additionally, no direct evidence of koala use (scat, sightings, Koala scratches) was observed
on site during botanical survey and tree survey.

Page 5

Results of the ecological assessment indicate that the proposed change to approval will result in a
net positive impact in terms of koala habitat retention and no significant loss of functional habitat
connectivity within the landscape.

6. Action:
   Provide a report prepared by a suitably qualified ecologist that:
   • identifies areas of existing mapped koala habitat on site and investigates mechanisms to
      protect these areas through a legal security mechanism such as an environmental covenant.
   • provides a map or shape file of the location of the covenant area. Demonstrates alternative
      development options that have been considered to retain more mapped koala habitat (e.g.
      all covenant locations that were considered), taking into consideration the results of koala
      habitat value assessments.
   • provides details of improvements to the identified covenant areas by removing weeds and
      planting koala food trees endemic to the site (based on the sites regional ecosystem).

Response:
Notwithstanding the proposed change is consistent with the development approval, an assessment
of Koala habitat values, including a Koala survey has been undertaken and detailed in the attached
Ecological Assessment Report.

As detailed in this report a targeted Koala survey was conducted over the entire site by OWAD
Environment on 20 April 2023 with a team of ecologists and a purpose-bred detection dog certified
by the Australian Canine Detection Certification Council for Koala and Quoll scat determination. In
addition any evidence of Koala usage (scat, sighting and Koala scratches) was also recorded during
a detailed tree survey and botanical survey, with over 100 hours spent on site between May 2022
and April 2023 by 4 qualified ecologists. This report and survey confirms that the site does not
currently form part of the home range of any individual Koala, nor has it been recently used by
Koalas. Additionally, no direct evidence of koala use (scat, sightings Koala scratches) was observed
on site during botanical survey and tree survey.

The report further confirms that the change provides an improved development outcome, as it:
• results in a net positive impact to potential fauna habitat on site
• does not result on any significant habitat loss
• does not result in barriers to fauna movement within the site or wider area.

Given that the change is consistent with the development approval an environmental covenant is not
relevant.

7. Action:
   It is advised that the applicant consider mitigation measures such as:
   • retaining koala habitat area in locations that will allow koalas to use and move through the
        site
   • retaining koala habitat area which have been identified through an ecological survey as
        being of higher use for koalas (e.g., retaining components of koala habitat areas with more
        records or other signs of koala use (i.e., scats or tree scratching) or areas that contain
        koala habitat trees preferred by koalas (e.g., blue gum))’
   • retaining particular koala habitat trees that koalas are using which have been identified
        through an ecological survey and ensuring that koalas can move safely between the koala
        habitat tree and other koala habitat areas

Page 6

   •   improving degraded koala habitat areas that are to be retained on the site by removing
       weeds and planting koala food trees endemic to the site (based on the sites regional
       ecosystem(s))
   •   minimising impacts on retained habitat and koalas using the area by:
          o providing a buffer between development and any retained koala habitat, and/or
          o managing edge effects on retained koala habitat including:
                   changes in soil condition, such as nutrients and erosion
                   altered hydrological flow
                   the introduction or increase of weed and exotic plant species
                   disturbances to vegetation
                   a modified fire regime
                   the introduction of predators to koalas
                   increased light, noise or dust.

Response:
Refer correspondence from Litoria Consulting included in Appendix C. As indicated, the attached
Ecological Assessment Report and originally submitted Vegetation Management Plan outline
avoidance, mitigation and management measures. Impact mitigation is achieved via the
implementation of detailed fauna management measures and development design measures
outlined in section 6.3 of the Ecological Assessment Report. Additional impacts result from the
proposed change are minor and mitigated by the fact that the change will result in a net positive
impact to koala habitat on the site.

8. Action:
   Provide the following information, prepared by a suitably qualified ecologist:
   • any actions that will be undertaken on land retained to avoid fragmenting koala habitat
      areas that will improve connectivity between koala habitat areas (e.g., removing barriers,
      revegetating with koala habitat trees, the density of plantings, the distance between planted
      trees, encouraging natural revegetation, incorporating principles of koala-sensitive design
      (described in the Koala-sensitive design guideline)).
   • provides an assessment of the connectivity values and safe koala movement opportunities
      that would exist on the site post-development.
   • identifies barriers to movement that will be proposed by the development (e.g. established
      roads, fences, and retaining walls, introduction of residential threats such as pools and
      dogs and areas without koala habitat trees that increase the time koalas would need to
      spend on the ground).
   • outlines measures that will be undertaken to ensure koalas can move safely within and
      between highly connected patches of koala habitat area.
   • provides justification for why the proposed measures are suitable for providing safe koala
      movement opportunities.

Response:
Refer attached Ecological Assessment Report, originally submitted Vegetation Management Plan
and correspondence form Litoria Consulting in Appendix C.

The EAR and VMP provide detailed development design and management measures which
demonstrate how the proposed change will not adversely impact the movement of koalas through
the site (Refer to Section 6.3 of the EAR). Whilst there are additional impacts resulting from the
proposed change to accommodate driveway access, these impacts are minor and unlikely to impact
koala movement, as the impact is located adjacent to an existing road. In addition, impacts are
mitigated by the fact that the proposed change will result in a net positive impact to koala habitat on

Page 7

site through the retention of additional vegetation. Retained vegetation will maintain physical
connectivity between the site and adjacent habitat, thereby reducing barriers to Koala movement
within the subject land.

Figure 1 of the Appendix C correspondence demonstrates additional areas of mapped Koala Habitat
Areas that will be retained as a result of the proposed change, along with the improved connectivity
to adjacent habitat areas. Refer to Section 5.3 in the EAR for additional details.

9. Action:
   The applicant should provide a report prepared by an appropriately qualified ecologist that:
   • identifies all MSES on site and provides a likelihood of occurrence list for these MSES
      based on the habitat values found on site.
   • demonstrates how impacts to the identified MSES have been avoided to the greatest extent
      possible.
   • where all or part of a MSES cannot be avoided, demonstrates how any impacts to MSES
      that cannot be avoided have been minimised and mitigated to the greatest extent possible
      (e.g., through alteration of proposed development configuration (multi-story instead of
      single-story buildings, smaller development footprint, planting on site, etc)).
   • provides a significant residual impact assessment for any residual impact on each identified
      MSES (after all avoidance, minimisation and mitigation measures have been=
      demonstrated) in accordance with:
          o Chapter 2A of the Queensland Environmental Offsets Policy for koala habitat
          o DSDMIP Significant Residual Impact Guideline provides for all other MSES
          o quantifies the maximum extent of proposed significant residual impact to each
               MSES both in area (ha) and on a plan.

Response:
Refer attached Ecological Assessment Report which includes an assessment against MSES. Also
refer correspondence from Litoria Consulting included in Appendix C. As indicated, the ecological
assessment report includes a significant residual impact (SRI) assessment (Refer Section 5.4 of the
EAR). The results of the SRI assessment indicate that the proposed change does not result in a
significant residual impact to applicable MSES.

In addition, the original approval included a condition for a monetary contribution for the offset of 48
koala habitat trees in accordance with the Policy for Offsets for Net Gain of Koala Habitat in South
East Queensland, which was current at that time (Refer Condition 106 of MCU 2008/176, encl.) A
monetary contribution of $44,160 ($920 x 48 trees) has already been made to Council to offset the
removal of 48 koala habitat trees, thus precluding the imposition of an additional offset condition as
stated under section 25A of the Environmental Offsets Act 2014 (Qld). In any case, the proposed
change results in a net increase in koala habitat retention compared to the existing approval.



                                 END INFORMATION RESPONSE

Page 8

Should you have any questions with respect to the above, please do not hesitate to contact me
direct.

Yours faithfully
PROJECT URBAN




Scott Sobey
DIRECTOR
Email: [email protected]

Page 9

URBAN ©)

APPENDIX A

 

State Code 6: PO26 — PO31 response

Page 10

Public passenger transport infrastructure and active transport

Performance Outcomes                        Acceptable Outcomes                            Comment

PO26 Upgraded or new public                 No acceptable outcome is prescribed.           Complies with PO
passenger transport infrastructure and
                                                                                           No changes to the public transport
active transport infrastructure is
                                                                                           infrastructure or active transport
provided to accommodate the demand
                                                                                           network has been made
for public passenger transport and
active transport generated by the
development.

PO27 Development is designed to             No acceptable outcome is prescribed.           Complies with PO
ensure the location of public passenger
                                                                                           A Porte cochere will be provisioned
transport infrastructure prioritises and
                                                                                           which will enable access for a 21 seater
enables efficient public passenger
                                                                                           bus which will connect to Noosa
services.
                                                                                           Junction Station to provide connections
                                                                                           to the wider public transport network.

                                                                                           The Porte cochere also allows for set
                                                                                           down areas for taxis and other car share
                                                                                           services

PO28 Development enables the                No acceptable outcome is prescribed.           Complies with PO
provision or extension of public
                                                                                           A Porte cochere will be provisioned
passenger services, public passenger
                                                                                           which will enable access for a 21 seater
transport infrastructure and active
                                                                                           bus which will connect to Noosa
transport infrastructure to the
                                                                                           Junction Station to provide connections
development and avoids creating
                                                                                           to the wider public transport network.
indirect or inefficient routes for public
passenger services.                                                                        The Porte cochere also allows for set
                                                                                           down areas for taxis and other car share
                                                                                           services

PO29 New or modified road networks          AO29.1 Roads catering for buses are            Complies with AO
are designed to enable development to       arterial or sub-arterial roads, collector or
                                                                                           TTM has provided a functional layout for
be serviced by public passenger             their equivalent.
                                                                                           Banksia Street/ Grant Street roundabout
services.
                                            AND                                            to be upgraded in accordance with
                                                                                           Austroads to cater for buses and service
                                             AO29.2 Roads intended to
                                                                                           vehicles accessing the site.
                                            accommodate buses are designed and
                                            constructed in accordance with:

                                            1. Road Planning and Design Manual,
                                            2nd Edition, Volume 3 – Guide to Road
                                            Design; Department of Transport and
                                            Main Roads;

                                            2. Supplement to Austroads Guide to
                                            Road Design (Parts 3, 4-4C and 6),

Page 11

                                         Department of Transport and Main
                                         Roads;

                                         3. Austroads Guide to Road Design (Parts
                                         3, 4- 4C and 6);

                                         4. Austroads Design Vehicles and Turning
                                         Path Templates;

                                         5. Queensland Manual of Uniform Traffic
                                         Control Devices, Part 13: Local Area
                                         Traffic Management and AS 1742.13-
                                         2009 Manual of Uniform Traffic Control
                                         Devices – Local Area Traffic
                                         Management;

                                         AND

                                         AO29.3 Traffic calming devices are not
                                         installed on roads used for buses in
                                         accordance with section 2.3.2 Bus Route
                                         Infrastructure, Public Transport
                                         Infrastructure Manual, Department of
                                         Transport and Main Roads, 2015.

PO30 Development provides safe, direct   No acceptable outcome is prescribed.       Complies with PO
and convenient access to existing and
                                                                                    A Porte cochere will be provisioned
future public passenger transport
                                                                                    which will enable access for a 21 seater
infrastructure and active transport
                                                                                    bus which will connect to Noosa
infrastructure.
                                                                                    Junction Station to provide connections
                                                                                    to the wider public transport network.

                                                                                    The Porte cochere also allows for set
                                                                                    down areas for taxis and other car share
                                                                                    services.

PO31 On-site vehicular circulation       No acceptable outcome is prescribed.       Complies with PO
ensures the safety of both public
                                                                                    A Porte cochere will be provisioned
passenger transport services and
                                                                                    which will enable access for a 21 seater
pedestrians
                                                                                    bus which will connect to Noosa
                                                                                    Junction Station to provide connections
                                                                                    to the wider public transport network.

                                                                                    The Porte cochere also allows for set
                                                                                    down areas for taxis and other car share
                                                                                    services

Page 12

URBAN ©)

APPENDIX B

 

Legal advice on Other Change assessment criteria

Page 13

CONNOR @ O’MEARA

solicitors

Our Ref: Michael Connor:JAB:2200194

20 July 2023

Andrew Stevens
Managing Director
Project Urban

BY EMAIL

Dear Andrew
3 - 7 Serenity Close, Noosa Heads

We are asked to advise about the assessment of a change application,
which is not a minor change, made to the Noosa Council on 10 October
2022' (“Change Application”).

Background

The land (“Land”) the subject of the Change Application is:
1. located at 3 - 7 Serenity Close, Noosa Heads;

2. described as Lots 10 and 11 on SP 195871;

3. has an area of 24,040 m?;

4. is currently included mainly in the Tourist Accommodation Zone
and partly in the Environmental Management and Conservation
Zone, pursuant to the Noosa Planning Scheme 2020. Also the Land
is affected by the Biodiversity, Waterways and Wetlands Overlay
(and identified as an area of biodiversity significance) and the
Protected Vegetation Overlay; and

*132008.176.05

level 4 10 eagle street
gpo box 2239 brisbane 4001
e [email protected]
00612867.D0CX Ww www.connoromeara.com

t 07 3221 3033
f 07 3221 6661

Page 14

5, has the benefit of a development approval given on 14 October
2011? (“Development Approval”) by the Planning and Environment
Court for an accommodation building and multiple dwellings.

The Development Approval, given by the Court, remains extant but has
not, as yet, been acted upon.

The Development Approval was last changed on 9 February 2017. The
changed approval authorises a development permit for a material change
of use for a “Resort Development comprising Multiple Dwelling (109
Dwelling Units) and Accommodation Building (90 Accommodation Units}
and Ancillary Facilities".

Changes in the legislative and statutory framework since the Development
Approval was given

Since the Development Approval was given, there has been a range of
changes in the statutory and regulatory framework against which
applications are considered, assessed and decided.

Three significant changes are relevant.

First, the Noosa Plan 2020 took effect on 31 July 2020, replacing the
Noosa Plan 2006.

Secondly, whilst the Development Approval was assessed and decided
under the Sustainable Planning Act 2009, that legislation has now been
repealed and replaced by the Planning Act 2076, which permits changes
other than a minor change.

Third, on 7 February 2020, the Nature Conservation and Other Legislation
(Koala Protection) Amendment Regulation 2020 amended the Planning
Regulation 2077 to regulate development which interfered with koala
habitat areas.

Development Approvals and Changing Them
Notwithstanding that the Development Approval was originally given in
2011, it still has the force of law and can be acted upon while it is

extant, notwithstanding changes in the planning scheme.

Indeed, the Development Approval is taken to be an approval under the
Planning Act 2076.

? P&E Appeal No. 178 of 2010, noting the assessment manager was the Sunshine Coast
Regional Council.

0061 2867.D0CX

Page 15

The assessment and decision making framework for a change application,
which is not a minor change, is set out in Section 82 of the Planning Act
2076. Subsection (2) of the provision states:

“82 Assessing and deciding change applications for other changes

(2)

For administering the change application, and assessing and
deciding the change application in the context of the

development approval, the relevant provisions apply—

a. as if-
i

i.

the responsible entity were the assessment
Manager; and

the change application were __the _ original
development application, with the changes
included, but was made when _the change

application was made; and

 

 

b. with necessary changes.

(4) To_remove any doubt, it is declared that the following matters
apply, only to the extent the matters are relevant to assessing and
deciding the change application in the context of the development

approval-
a. the assessment benchmarks;

(underlining added)”

The phrase “relevant provisions" is defined for the purposes of s 82 as:

“(6)

In this section-

relevant provisions means-

(a) section 45(6) to (8); and

(b) part 2, division 2, other than section 51; and
(c) part 3, other than sections 63 and 64(8)(c); and
(d) the development assessment rules.”

This means two important things for present purposes.

First, a change application is taken by law to be the original development
application, with the changes included, but made when the change
application was made.

Secondly, and pursuant to section 45(7) of the Planning Act 20176, the
assessment to be undertaken must be carried out against the assessment

00612867.D0CX

Page 16

benchmarks in a categorising instrument for the development in effect
when the change application is made.

The local categorising instrument for the assessment is the Noosa Plan
2020 because that is the local categorising instrument in force when the
Change Application was made. Further, we note that the assessment of
the Change Application must also be against the State Development
Assessment Provisions (“SDAP”), including State Code 25.

Having said that, the exercise to be undertaken in carrying out the
assessment is different to a normal development application given the
effect of the words “in the context of the development approval" found in
section 82 of the Planning Act 2016.

The Court, in Catterall & Ors v Moreton Bay Regional Council & Anor
[2020] QPEC 52, has said the following about the phrase “in the context
of the development approval":

“The purpose of this phrase is to make clear that the assessment
and decision making process occurs in the context that the
application is one to change an existing development approval, as
distinct from a fresh development application. In practical terms,
this means the assessment and decision making process for a
change application under s 82 of the PA is founded upon, but not
limited to:

(a) an identification of the change/s proposed to the
development approval;

(b) an identification of the planning issues, be they positive or
negative, arising for consideration as a consequence of the
change/s proposed to the development approval; and

(c) an assessment of the planning issues arising as a
consequence of the change/s to the development approval,
having regard to the requirements of “relevant provisions’,
and assessment benchmarks, to the extent they are
relevant.”

What the above means is that the Development Approval represents a
starting point. In carrying out the assessment, the assessment manager is
required to filter out certain aspects of that assessment against the
background of the Development Approval.

By way of example, in the present circumstances, there is no proposal to

increase the height of the built form of the development. In those
circumstances, it is impermissible for the assessment manager to carry

00612867.DOCX

Page 17

out an assessment against provisions of the planning scheme which
regulate building height.

It is also important to note the task required when a change is proposed.
If the approved built form had a height of 3 storeys and the change
proposed to increase the height to 4 storeys, the relevant exercise in
those circumstances would be to assess the additional storey, not the 4

storeys in total.

Similarly, where there is a change in the building footprint which impacts
on koala habitat, it is only the additional impacts beyond the impacts of
the approved development which can be permissibly assessed.

Koala Legislation

On 1 September 2017, the Nature Conservation (Koala) Conservation
Plan, mapped the Land as a koala habitat area, but not a koala priority
area.

On 7 February 2020, the Nature Conservation and Other Legislation
(Koala Protection) Amendment Regulation 2020 amended the Planning
Regulation 2077 to regulate development which interfered with koala
habitat areas.

Part 10 of Schedule 10 of the Planning Regulation 2017 ("PR") applies to
development on a lot that is completely or partly in the SEQ region and
Division 3 provides for the circumstances in which development
interfering with koala habitat in a koala habitat area which is not a koala
priority area is assessable development. That is, development. is
assessable development to the extent that it will interfere with a koala
habitat in an area that is a koala habitat area but is not a koala priority
area.

However, the provisions which make that type of development assessable
do not apply to the extent that the development is consistent with a
development approval that is in effect for the premises on which the
development is carried out and was given for an application that was
properly made before 7 February 2020.°

The relevant assessment benchmarks are SDAP.* State Code 25 is the

relevant part of the SDAP which applies to development in South East
Queensland koala habitat areas.

3 PR, Sch 10, Pt 10, Div 3, s 16B(2)(e).
* PR, Sch 10, Pt 10,, Div 3, SubDiv 3, Table 1, Item 4.

00612867.DOCX

Page 18

Interpretation of “consistent”

“Consistent” for the purposes of the PR is not defined and there has not
been judicial consideration of “consistent” in this particular context. It
follows, consistent with the established canons of statutory
constructions, that the word is to take its plain and ordinary meaning.°®

The ordinary meaning of the word “consistent” is:

6. agreeing or accordant; compatible; not self-opposed or self-
contradictory;

7. constantly adhering to the same principles, course et.°®

In addition to the above, we note that “consistent” has been judicially
considered for the purposes of other Queensland and interstate planning
contexts.

In Lake Maroona Pty Ltd v Gladstone Regional Council,’ Bowskill DCJ
considered the meaning of “consistency” for the purposes of s 388(1)(a)
of the Sustainable Planning Act 2009 (Qld). In that decision, the Court
considered several similar cases from New South Wales that had
interpreted the meaning of “consistent” for the purposes of planning
legislation. Her Honour preferred the view expressed in Gillespies v
Warringah Council.® In that case, Bignold J held that “consistent” had its
ordinary and natural meaning as defined in the Macquarie Dictionary. His
Honour held that the Macquarie Dictionary meaning of “compatible” as
“capable of existing in harmony" was applicable to the interpretation of
“consistent” in the context of the Warringah Local Environment Plan
2000.°

In Friends of Malua Bay Inc v Perkins'® Craig J adopted the approach
taken in Gillespies holding that it was appropriate to regard “consistent”
as being synonymous with “compatible”. Considered in both Gillespies
and Malua Bay was the primary judgment of Clarke JA in Coffs Harbour
Environment Centre Inc v Coffs Harbour City Council and Another''. \|n
that case the meaning of consistent was narrowed to “development not
antipathetic”. However, that approach was disavowed in both Gillespies
and Malua Bay.

5Project Blue Sky Inc v Australian Broadcasting Authority [1998] 194 CLR 355.
®Macquarie Dictionary (7" ed, 2017) ‘consistent’.

712017] QPEC 25 (‘Lake Maroona’).

®(2002) 124 LGERA 147 (’Gillespies').

Sel 12(3)(b).

'0(2014) 203 LGERA 14 (‘Malua Bay’).

(1991) 74 LGRA 185.

0061 2867.DOCX

Page 19

Continuing that long line of authority, Bowskill DCJ concluded that “the
natural and ordinary meaning of the word “consistency”, ought to be
adopted in construing [the relevant provisions]".'? Her Honour also held
that determining the consistency of an approval with current laws and
policies is to determine if the approved development is capable of existing
in harmony with those laws and policies. Her Honour stated that
“consistency” is a more flexible concept than whether the development
conflicts with the planning scheme. Instead, development may still be
compatible even if it is at variance with some aspects of the planning
scheme.

It follows that what emerges from the above cases is that the term
“consistent”:

1. does not mean precisely the same;

2. provides for a degree of flexibility; and

3. requires an element of compatibility and harmony.
Discussion

Relevantly, the starting point is to consider whether the changed
development is “consistent” with the Development Approval.

Given that consistency between the Development Approval and the
Change Application is a question of fact and degree, there are a few
indicators which may be relevant in determining whether, from a
perspective of koala habitat ecology, the two are consistent with one
another.

Firstly, in addition to the trees required to be retained by the Development
Approval, the development as it is proposed to be changed provides for a
net reduction in the area to be disturbed, largely as a consequence of
additional vegetation to be retained, of 7,970m?.

Second, we note that although the proposed development’s site cover is
increasing, that increase is modest and limited.

2 (24),

0061 2867.D0CX

Page 20

Third, the legislative context for the amendment to the PR is also relevant
to the assessment of consistency with the original approval. In that
sense, the planning purpose of the amendments to the PR was to provide
for the protection of koala habitat areas. Accordingly, where the
ecological outcomes for koala habitat as a consequence of the proposed
change are no worse (and indeed are likely better) than the outcomes
approved by the Development Approval, that factor is another indicator of
consistency between the proposed changed development and the
Development Approval.

In those circumstances, where the substance of the change is not
touching upon the matters relevant to ecology, or put another way it is
not changing those outcomes (at least in an adverse way), there is an
obvious level of harmony and compatibility between the Development
Approval and the change the subject of the present change application. It
follows, given that harmony and compatibility, we think it is open to
conclude that the change is “consistent” with the Development Approval.

Putting aside the question of whether the changed development is
“consistent” with the Development Approval, there are a few things to
note:

1, the whole of the development is not to be reassessed by the other
change process. Instead, it is a discrete analysis of the changes
which arise in the context of the Development Approval. By simple
reference to the site cover, we note that the site cover is increasing
from 34% to 40%. It follows then, that the assessment is not to
be carried out about the entire footprint covering 40%, but rather
by reference to the additional 6%;"°

2. in that regard we have considered the arborist report of 7 October
2022. At page 7 of that report, we note that it is identified that “as
the proposed development is for a change to an existing approval,
tree survey was limited to areas currently zoned Environmental
Management and Conservation, together with areas outside of the
building footprint indicated by the approved plans”. |In our view,
that approach is entirely appropriate and correct at law. Put another
way, the report assesses:

(a) the additional 6% of site cover; and

(b) matters arising from changes to assessment benchmarks
since the Development Approval was originally given; and

'3 assuming that 34% of the 40% now proposed is coincidental with the site cover of

the approved development.

0061 2867.DOCX

Page 21

3. in contrast, we note that the information request given by the State
Assessment Referral Agency (“SARA”) dated 6 December 2022
appears to proceed on an incorrect footing. That is, the issues with
respect to State Code 25 appear to be premised upon the Change
Application representing an opportunity to reassess the whole of
the development afresh. In our view that is wrong and inconsistent
with the law and recent jurisprudence of the Planning and
Environment Court. An example of the incorrect approach are the
comments made in Issue 5 of the SARA information request which
identifies, “the application material has not provided an assessment
of the koala habitat area on site. An arborist report was provided
for the additional area of proposed clearing, however an ecological
assessment is required for the whole site” (emphasis added). That
approach stands in stark contrast with the approach identified in
both the explanatory notes to the Planning Act 2076 in respect of
section 82 and the law as identified by the decision in Catterall &
Ors v Moreton Bay Regional Council & Anor [2020] QPEC 52.

On the strength of the above, it is our view that the approach identified
by SARA in the information request and, in particular but not limited to
Issue 5, fails to properly understand the required assessment and seeks to
impermissibly assess and comment upon elements of the Development
Approval which are not changing.

Conclusion

In our view:

1. given the changed development is “consistent” with the
Development Approval, the relevant considerations arising from the
change to the koala regulations in the PR are not engaged; and

2. even if we are wrong about the above, given the statutory exercise
that is required by the PA, SARA ought to be invited to carry out

its assessment according to law.

Yours faithfully
CONNOR O’MEARA

KAUXLOMN -

“Liability limited by a scheme approved under professional standards legislation”

0061 2867.D0CX

Page 22

URBAN ©)

APPENDIX C

 

Litoria Consulting correspondence

Page 23

litoria consulting

PO Box 461
Paddington Q 4064

Level 3/22 Wandoo Street
Fortitude Valley O 4006

T 07 3862.4855

[email protected]
litoria.com.au

Your Ref:
Our Ref: 22011

12 July 2023

Paul Gleeson

Principal Planning Officer

State Assessment and Referral Agency

via email: [email protected]

Dear Paul,

RE: INFORMATION REQUEST RESPONSE - 2210-31715 SRA - 3-7 SERENITY CLOSE, NOOSA
HEADS (LOTS 10 & 11 ON SP195871)

| refer to SARA’s information request (6 December 2022) associated with the change
application located at the abovementioned address. Our response deals with items 3 to 9
of the information request.

3. The application material has not provided a response against State code 25 or any
information that can be used to address State code 25.

The information request given by SARA (6 December 2022) appear to be premised
upon the Change Application representing an opportunity to reassess the whole of
the development afresh. Where there is a change in the building footprint which
impacts on koala habitat, it is only the additional impacts beyond the impacts of
the approved development which can be permissibly assessed. Given the changed
development is consistent with the original development approval, the relevant
considerations arising from the change to the koala regulations in the Planning
Regulation 2017 are not engaged. An Ecological Assessment Report (Litoria
Consulting, v 1.0, July 2023) (EAR) (encl.) has been prepared which demonstrates
that the proposed change to the existing development approval will result in a net
gain in koala habitat through the additional retention of areas containing ecological
values.

689 LLS OOL SZ Nav

Page 24

4, The application material mentions a previous development approval over the lot issued
by Noosa Shire Council. The development approval and development plans were not
provided with the application material.

Please refer to Appendix 1 of the EAR which contains the development approval
and development plans.

5. The application material has not provided an assessment of the koala habitat area on site.
An arborists report was provided for the additional area of proposed clearing, however an
ecological assessment report is required for the whole site.

An ecological assessment was undertaken generally in accordance with the Noosa
Council Planning Scheme Policy 3 - Ecological assessment guidelines. As part of
the assessment, a desktop review and field investigations, including targeted koala
survey with purpose-bred detection dogs, was undertaken to assess impacts to
koala habitat on site. The results of the koala survey indicated no evidence of koala
on the site, with no evidence of either individuals or scat present. The results of the
survey are contained in Section 4.5.2 and Appendix 5 of the EAR.

Results of the ecological assessment indicated that the proposed change to the
approval will result in a net positive impact in terms of koala habitat retention and
no significant loss of functional habitat connectivity within the landscape.

6. The application material has not discussed how the remaining mapped koala habitat on
site will be protected in perpetuity. The application material should discuss legal security
measures such as environmental covenants to protect the proposed eco zones.

Retention of mapped koala habitat on site can be conditioned as part of a
development permit.

7. The application material does not demonstrate any mitigation of impacts to koala habitat.

The EAR and Vegetation Management Plan (Litoria Consulting, Issue A, 7 October
2022) (VMP) (encl.) outline proposed avoidance, mitigation and management
measures.

Impact mitigation is achieved via the implementation of detailed fauna
management measures and development design measures outlined in Section 6.3
of the EAR.

Additional impacts resulting from the proposed change are minor and mitigated by
the fact that the proposed change will result in a net positive impact to koala
habitat on site.

8 The application material has not demonstrated how the design of the proposed
development will not adversely impact the movement of koalas through the site.

The EAR and VMP provide detailed development design and management
measures which demonstrate how the proposed change will not adversely impact

LORS 215

Page 25

the movement of koalas through the site (Refer to Section 6.3 of the EAR). Whilst
there are additional impacts resulting from the proposed change to accommodate
driveway access, these impacts are minor and unlikely to impact koala movement,
as the impact is located adjacent to an existing road. In addition, impacts are
mitigated by the fact that the proposed change will result in a net positive impact
to koala habitat on site through the retention of additional vegetation. Retained
vegetation will maintain physical connectivity between the site and adjacent
habitat, thereby reducing barriers to Koala movement within the subject land.
Figure 1 demonstrates additional areas of mapped Koala Habitat Areas that will be
retained as a result of the proposed change, along with the improved connectivity
to adjacent habitat areas. Refer to Section 5.3 in the EAR for additional details.

9. The application material has not discussed matters of State environmental significance
(MSES) that could occur on the site or potential impacts to MSES as a result of development
of the site. An arborists report was provided for the additional area of proposed clearing,
however an ecological assessment report is required for the whole developments impacts
on MSES.

A significant residual impact (SRI) assessment was undertaken as part of the
ecological assessment (Refer Section 5.4 of the EAR). The results of the SRI
assessment indicated that the proposed change does not result in a significant
residual impact to applicable MSES.

In addition, the original approval included a condition for a monetary contribution
for the offset of 48 koala habitat trees in accordance with the Policy for Offsets for
Net Gain of Koala Habitat in South East Queensland, which was current at that time
(Refer Condition 106 of MCU 2008/176, encl.) A monetary contribution of $44,160
($920 x 48 trees) has already been made to Council to offset the removal of 48
koala habitat trees, thus precluding the imposition of an additional offset condition
as stated under section 25A of the Environmental Offsets Act 2014 (Qld). In any
case, the proposed change results in a net increase in koala habitat retention
compared to the existing approval.

LORS 315

Page 26

Please note, the EAR and assessment of environmental impacts were conducted using
land parcel boundaries obtained by the Department of Resources in 2022. It has come to
our attention that there has been an update to the land parcel boundaries in 2023,
resulting in slight variations in lot sizes and extents. However, based on these changes, it is
unlikely that the assessment outcomes presented in the EAR will be significantly different.

| trust that the enclosed information is satisfactory and assists SARA in approving the
application; however, if there are any matters that you wish to discuss, please do not

hesitate to contact Freya Jassim from our office on [email protected] or 07 3852
4855.
Sincerely,

 

Daniel Clowes BAppSc (EnvSc) DipArb MEIANZ MESA MISA
Director

Encl.: Arborist Report and Vegetation Management Plan (Litoria Consulting, Issue A, 7
October 2022)

Ecological Assessment Report (EAR) (Litoria Consulting, v 1.0, July 2023)

LORS 4s

Page 27

 

Legend y
[os ~\ ~ §

Cadastre
CJ ‘Lot bouncary

| Easement
‘Koala Hapliat Areas v3.0
HBB tre ose Havnaréeas

Proposed charge
[J Perosec enange oorpent

Addtiona areas of retained Kosta Habtat Areas

   
 
 
 
 
  
  

 

 

 

1 Department of Environment and Science (2022). South East Queensland Koala Conservation Strategy 2019-2024 (GIS Dataset).
State of Queensland (Department of Environment and Science).

LO ORIAS 515

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.