Park Contributions
26. A Park contribution of $1,529 towards the acquisition of additional parkland or the
improvement of existing parkland and facilities in the locality shall be paid to the Council prior
to obtaining a Development Permit for Operational Works in accordance with Council’s
Planning Scheme Policy PSP24 Park Requirements for Development Applications. This
amount will be subject to variations in the Consumer Price Index, All Groups Brisbane from
September 2005 until the date of payment.
Frontage Works
27. Footpath improvements such as topsoiling, grassing, and tree planting are required to the
Corsair Crescent frontage of the site in accordance with Planning Scheme Policy PSP1
Landscaping Guidelines. Grass shall be couch, free of weeds.
28. A new 1.2m wide concrete path shall be constructed along the whole of the Corsair Crescent
frontage of the site. The path shall be constructed in accordance with Council’s design
standards and to an alignment that protects any significant vegetation or any underground
services.
29. All paths shall be designed and constructed to ensure pedestrian safety using non-slip
materials and to produce an evenly graded surface finish.
30. All redundant vehicular crossings to the site and redundant stormwater outlet features shall be
removed and replaced by kerb & channel, footpath paving and landscaping such as trees and
grasses in accordance with Council’s Standard specifications prior to commencement of the
use permitted by this permit.
Pathway Contributions
31. A pathway contribution of $344 towards external major pathways, in accordance with Planning
Scheme Policy PSP41 Pathway Trunk Network Contributions, shall be paid to the Council
prior to obtaining a Development Permit for Operational Works. This amount will be subject to
variations in the Consumer Price Index, All Groups Brisbane from September 2005 until the
date of payment.
Stormwater Drainage
32. All stormwater drainage shall be collected on site and discharged so there is no net increase
in stormwater runoff from the site. Stormwater drainage permitted to drain from the site shall
be discharged to Council’s kerb & channel street drainage system in Corsair Crescent. Plans
of the drainage design shall be prepared by a Registered Professional Civil Engineer and
submitted to Council prior to obtaining a Development Permit for Operational Works.
The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street
drainage system at any one location is 25 litres/second.
33. Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank
(minimum storage 3000 litres per dwelling unit) that is plumbed to service the toilets in the new
dwelling and landscaping areas. The design of the rainwater storage system shall be to the
satisfaction of the Manager Plumbing Services and the location clearly shown on the plans
submitted for Building Works approval.
34. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
35. The site shall be connected to Council’s existing sewerage reticulation systems and be
constructed in accordance with Council’s standards and requirements at no cost to Council.
36. The existing sewer connection shall be temporarily capped off and reconnected once the new
duplex is completed. In this regard a permit from Council’s Plumbing Services Section shall be
obtained prior to any works commencing.
Page 4 of 15
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Change to an Existing Approval [As Published]Related documentApplication case desk ↗
About this file
- File size
- 304 KB (small file)
- File type
No other editions are linked here.