Appendix A - SDAP - State Code 16 - Native vegetation clearing response
Performance outcomes Acceptable outcomes Response
AO116.3 Clearing is for the purpose of natural
disaster preparation and does not exceed the
areas prescribed in reference table 1 of this code.
PO117 Where clearing of vegetation in a regional No acceptable outcome is prescribed.
ecosystem does not maintain the composition,
structure and function of the regional ecosystem,
and cannot be avoided and has been mitigated, the
cleared area is rehabilitated.
Maintaining the composition, structure and function of the regional ecosystem (natural channel diversion and contaminants removal)
PO118 Clearing of vegetation maintains the AO118.1 Clearing retains all of the following:
composition, structure and function of the regional 1. habitat trees;
ecosystem. 2. mature trees; and
3. the natural floristic composition and range of
sizes across the application area.
PO119 Where clearing of vegetation in a regional No acceptable outcome is prescribed.
ecosystem does not maintain the composition,
structure and function of the regional ecosystem,
and cannot be avoided and has been mitigated, the
cleared area:
1. is rehabilitated; or
2. where the cleared area cannot reasonably be
rehabilitated, an offset is provided for any
acceptable significant residual impact.
Duration of clearing, preventing land degradation, and maintaining biodiversity, ecological processes and regional ecosystems (Land Restoration,
Natural Disaster Preparation and Contaminates Removal)
PO120 Clearing occurs only during a period that: No acceptable outcome is prescribed.
1. will not contribute to land degradation; and
2. ensures the ongoing maintenance of ecological
processes and biodiversity; and
3. maintains the regional ecosystem.
Table 16.12: Control non-native plants or declared pests
Performance outcomes Acceptable outcomes Response
Clearing avoids and minimises impacts
PO121 Clearing of vegetation and adverse No acceptable outcome is prescribed.
impacts of clearing vegetation do not occur unless
the application has demonstrated that the clearing
and the adverse impacts of clearing have been:
State Development Assessment Provisions v3.0
State code 16: Native vegetation clearing Page 38 of 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original