Notes: FSL
- Place the rootball on a firmed base to achieve required FSL. Macrophyte planting with root Jute mesh/coir netting. With Mulch
- Thoroughly water the root ball immediately after planting. ball fully into media and pull 300mm long pins at twice
Notes: - to 100mm depth
- Number of stakes will vary with pot size. Refer plant schedule. foliage through netting recommended rate to prevent
- Place the rootball on a firm base.
- Cultivate sides of excavated hole 50mm. the mesh from lifting.
- Thoroughly water the root ball immediately after planting. Soil blend or site topsoil
- Cultivate sides of excavated hole 50mm deep. - to 300mm depth
- Do not disturb kerb, road pavement or road side drainage works. Filter media and drainage per
- Tease out roots on side of rootball when planting. engineer. Filter media to contain
75mm thick coarse straw/ sugar
- Ensure top of rootball is not buried; expose and set flush with finished level. 5% organics per water by
cane mulch with minimal fines.
design guidelines Cultivated subgrade
- to 150mm depth
Hardwood Stake:
25x25x90mm Place 600mm
into the ground. Do not
place through rootball.
Secure with ties by looping
in a figure eight pattern.
3 BIO-BASIN PROFILE 4 GARDEN BED PROFILE
CD-200 1:10@A1, 1:20@A3 CD-200 1:10@A1, 1:20@A3
Hardwood stake: Place 600mm
Mulch: Pull away from
into the ground. Do not place
base of plant.
through rootball. Secure with
Form an earthen basin ties by looping in a figure eight
around base of plant. pattern. FSL
Turf as specified Notes:
(X)
Raise plant 50mm above - All timber to be CCA pressure treated to
finished surface level. Topsoil AS1604, Hazard 5, rough sawn pine. Timber edge
Mulch: Pull away from base - to 100mm depth - All timber edges to be arissed to comply
Topsoil blend of plant. with council standards.
Fertiliser: Do not allow Form an earthen basin Cultivate subgrade - All timber ends to have one coat of Stakes
contact with roots. around base of plant. - to 150mm depth Cuprinol or equal prior to installation.
Existing subgrade - Stakes to be 400mm into ground at max.
1200mm centres, or as required to obtain Existing/compacted
Water retention additive /subgrade/subase
smooth curves. Top of stake to finish
Topsoil blend 20mm below top of timber edge. Where
min 300
timber edges meet at corners provide
1 140-300mm PLANTING Water retention additive double stakes.
CD-200 1:10@A1, 1:20@A3 5 TURF PROFILE - All fixings to be hot dipped galv.
Fertiliser: Do not allow 1 CD-200 1:5@A1, 1:10@A3 - Leading edge is to be free of burrs and
fertiliser to come in 1 splinters.
contact with roots.
width (w)
10 - 20mm Drainage gravel TIMBER EDGE STAKES (X) = Height above
2xw FIXINGS
38 50 finished surface level
50mm Bugle Headed
FLUSH
Batten Screws.
2 45-200ltr PLANTING
100
20mm 75mm Bugle Headed
CD-200 1:10@A1, 1:20@A3 Batten Screws.
100mm
100mm Bugle Headed
150mm Batten screws.
100x38mm
50x50mm
Paling - refer to notes
Post - refer to notes 6 EDGE TYPE 1
CD-200 1:5@A1, 1:10@A3
Timber garden edge
Rail - refer to notes
Fence Type 1 Notes:
eq.
G.L. NOTE: FENCING TO BE COORDINATED WITH
1. Palings to be ACQ pressure treated pine 100 X 16mm to
RETAINING WALLS. WHERE NECESSARY SEEK
Footings - Round top of AS1604 Hazard 3. Fix palings with 2 (No.) 50mm x 2.5mm
STRUCTURAL DESIGN ADVICE ON
footings to shed water. screw shank or ring shank HDG nails to each rail. INCORPORATING FENCE POSTS INTO
1800
- Refer to Engineer's drawings. 2. Paling locations are to be fixed to rails and sleepers as RETAINING WALL STRUCTURES PRIOR TO
above. Overlap of palings to be 30mm. 3. Posts to be ACQ ORDERING MATERIALS AND COMMENCING
treated HWD to AS1604, Hazard 5, refer Specification. All post CONSTRUCTION
to have no heart (50mm from centre of pith). Aris all edges.
eq.
All posts to be 100 x 100mm, evenly spaced with a maximum
spacing of 2400mm.
Capping - 125x25mm Corner posts and end posts to have footings to a depth of
1200mm.
Post 4. Rails to be ACQ treated Pine to AS 1604, Hazard 3 100 x
100
25
G.L. 100 50mm as per spec. Butt join rails as shown on alternative
Rail posts where possible. Screw rails to posts with 1(No.) Type 17
100mm Bugle Head Batten Screws. Aris all edges.
Paling 5. Capping to be ACQ pressure treated pine to AS1604,
Hazard 3 100 x 25mm. Screw capping to rail with 1(No.) Type
1000
17 Bugle Head Batten Screws @ 600 cts. Arris all edges.
6. Fittings are to be hot dipped galvinised for all screws and
fittings. Coat with a film of grease or a bitumestic product
10mm dia. Gravel before use.
nom.100
40 30
350dia. Paling
max.2400 centres
Rail
Capping rail over
Post
7 FENCE TYPE 1 Butt join rails as shown
CD-02 1:20@A1, 1:40@A3
1.8m high timber paling fence
Revision Date Amendment Drawn Checked
APPROVAL ONLY
CONSTRUCTION DETAILS NOT FOR CONSTRUCTION
A
B
17.08.2022
23.01.2023
For Approval
For Approval
XL
LS
CS
CS
CD-200 scale as noted
9 KAURI STREET, COOROY
JOB NUMBER: 22332 CLIENT NAME: SUNSHINE GROVE PTY LTD.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to Further advice - 22332_OPW [B].pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.