Skip to the record
Beware of cheap imitations.

Original source · versioned page text

Report on Geotechnical Investigation - 11 Senegal Rise

of 30

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

                                                                                                 51 640 311 842
                                                                                                     CONTACT
                                                                                    [email protected]
                                                                                             arcosgroup.com.au
                                                                                                       OFFICES
                                                                         Sunshine Coast | Brisbane | Gold Coast




•    Completed platforms should be sealed with a minimum 250 mm layer of relatively
     granular material (CBR15% or greater) to minimise the effects of relatively clayey
     subgrades drying out leading to excessive cracking.
•    Earthworks activities should be undertaken in relatively homogenous sequences where
     achievable (ie. do not place “pockets” of gravel material next to impermeable clays as this
     will lead to zones where water could become trapped).
•    Fill material will be subject to potential settlement post placement. Well compacted fill
     placed in accordance with AS3798 and otherwise, good earthworks procedure should
     typically be subject to settlement in the order of 0.5% to 1.0% of the fill thickness over a
     log cycle of time.

Arcos can assist in preparing earthworks documentation or guidelines for contractors to
adhere to in order to achieve an efficient and “fit for purpose” end product.


8.2 Retaining Structures
Retaining walls must be designed by a suitably qualified and experienced engineer and
preferably in accordance with AS 4678. The geotechnical parameters for use in design of either
flexible or rigid wall systems are presented in Table 2.


Passive forces should be ignored in areas where disturbance may occur (ie. future trenching
or earthworks processes).


Compaction for retaining wall backfill should be undertaken with due care. Layers should be
placed thinner than for normal earthworks processes (say a maximum layer thickness of
100 mm) and compacted using light weight equipment such as hand controlled compactive
equipment to minimise the stresses on the wall. If hand controlled equipment is not practical,
temporary wall propping will be required.


Walls will need to incorporate full height drainage in accordance with good design practice to
minimise hydrostatic pressure. The below parameters do not include surcharge loadings.


Table 2: Retaining Wall Parameters (Unfactored)
                                          Unit Weight       Friction Angle         Drained Cohesion
                  Material
                                           (kN/m3)                (Ø)                    (c’)

                 Stiff Clays                   19                 26                             3
                 VLS Rock                      20                 30                          5-10
Notes:   VLS -     Very Low Strength




06 Aug 2021                                             Proposed Slope Stability and Retaining Wall
Log in to download the original file

Report on Geotechnical Investigation - 11 Senegal Rise.pdf · 6.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.