Council archive · source document
TPC 1469 - Change to Existing Approval (minor change to shade sails) [As Published] · 51981.3375.02
Officer: Denis Wallace
Direct Telephone: (07) 5449 5179
Response Address: Locked Bag 72
Sunshine Coast Mail Centre QLD 4560
Email: [email protected]
Our Reference: TPC 1469
Your Reference:
8 July 2010
Breffney CTS 9466
CARE North Shore Body Corporate
936 David Low Way
MARCOOLA QLD 4564
Dear Sir / Madam
Re: Change to Development Approval TPC1469 for rooftop shade sail structures at
4 Avocet Parade, Peregian Beach described as Lots 0-4 BUP5739,
I refer to your request to make a change to the above development approval. On 5 July 2010 Council
decided to: -
Approve the change subject to the following additional conditions:
1. The development is to be undertaken in accordance with the approved plans, being sketch
plan number SK-1 “Plan View and Side View” dated 11 July 2009 and as may be amended by
the conditions herein.
2. Shade cloth or similar non-reflective material shall be applied to the top side of the sail
structures to reduce glare to neighbouring residences.
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Sustainable Planning Act 2009 is also attached.
Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.
Yours faithfully,
Denis Wallace
Senior Development Planner
Enc. Appeal Rights
Page 1 of 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 2 pages
Page 2
2007/2463
Appeal Rights
INTEGRATED PLANNING ACT 1997 & 1998 REGULATION
The following is an extract from the Integrated (5) If an application is processed under section
Planning Act (Chapter 4). 6.1.28(2), appeal rights for submitters for the application
are available only for the aspects of the development
Division 8 - Appeals to court relating to that would have required public notification under the
development applications repealed Act.
Appeals by applicants (6) If an application involves assessment against a
4.1.27.(1) An applicant for a development application may concurrence agency code, appeal rights for submitters
appeal to the court against any of the following- for the application are not available against the part of
the approval that represents the concurrence agency’s
(a) the refusal, or the refusal in part, of a development response for the code.
application;
Appeals by advice agency submitters
(b) a matter stated in a development approval, including
any condition applying to the development, and the 4.1.29.(1) An advice agency may, within the limits of its
identification of a code under section 3.1.6;1 jurisdiction, appeal to the court about the giving of a
development approval for a development application if-
(c) the decision to give a preliminary approval when a
development permit was applied for; (a) the development application involves impact
assessment; and
(d) the length of a relevant period;
(b) the advice agency told the applicant and the
(e) a deemed refusal. assessment manager to treat its response to the
(2) An appeal under subsection (1)(a) to (d) must be application as a submission for an appeal.
started within 20 business days (the “applicant’s appeal
(2) The appeal must be started within 20 business
period”) after the day the decision notice or negotiated
days after the day the decision notice or negotiated
decision notice is given to the applicant.
decision notice is given to the advice agency as a
(3) An appeal under subsection (1)(e) may be started at submitter.
any time after the last day a decision on the matter should
have been made. Appeals for matters arising after approval given
(co-respondents)
Appeals by submitters
4.1.30.(1) For a development approval given for a
4.1.28.(1) A submitter for a development application may development application, a person to whom any of the
appeal to the court about- following notices have been given may appeal to the
(a) the giving of a development approval, including any court against the decision in the notice-
conditions (or lack of conditions) or other provisions (a) a notice giving a decision on a request for extension
of the approval; or of the relevant period for an approval;
(b) the length of a relevant period for the approval. (b) a notice giving a decision on a request to make a
(2) The appeal must be started within 20 business minor change to an approval.
days (the “submitters appeal period”) after the day the (2) The appeal must be started within 20 business
decision notice or negotiated decision notice is given to days after the day the notice of the decision is given to
the submitter. the person.
(3) If a person withdraws a submission before the (3) Subsection (1)(a) does not apply if the approval
application is decided, the person may not appeal the resulted from a development application (superseded
decision. planning scheme) that was assessed as if it were an
(4) If an application involves both impact assessment application under a superseded planning scheme.
and code assessment, appeal rights for submitters are
(4) Also, a person who has made a request
available only for the part of the application involving
mentioned in subsection (1) may appeal to the court
impact assessment.
against a deemed refusal of the request.
(5) An appeal under subsection (4) may be started
at any time after the last day the decision on the matter
should have been made.
1
Section 3.1.6 (Preliminary approval may override local
planning instrument)
2 of 3
Page 3
2007/2463
Division 9 - Appeals to court about other matters 4.2.9(1) An applicant for a development application may
appeal to the Building and Development Tribunal against
Appeals for matters arising after approval given any of the following-
(no co-respondents)
(a) the refusal, or the refusal in part, of a development
4.1.31.(1) A person to whom any of the following notices application;
have been given may appeal to the court against the
decision in the notice-
(b) a matter stated in a development approval, including
(a) a notice giving a decision on a request to change or any condition applying to the development, and the
cancel a condition of a development approval. identification of a code under section 3.1.6;3
(b) a notice under section 6.1.442 giving a decision to (c) the decision to give a preliminary approval when a
change or cancel a condition of a development development permit was applied for;
approval.
(d) the length of a period mentioned in section 3.5.21
(2) The appeal must be started within 20 business relevant period;
days after the day the notice of the decision is
given to the person. (e) a deemed refusal.
(3) Also, a person who has made a request (2) An appeal under subsection (1)(a) to (d) must be
mentioned in subsection (1)(a) may appeal to the started within 20 business days (the “applicant’s
appeal period”) after the day the decision notice or
court against a deemed refusal of the request.
negotiated decision notice is given to the applicant.
(4) An appeal under subsection (3) may be started
(3) An appeal under subsection (1)(e) may be
at any time after the last day the decision on the
started at any time after the last day a decision on the
matter should have been made.
matter should have been made.
Appeals against decisions to change approval conditions
under the repealed Act
The Registrar for the Building and Development
Tribunal may be contacted at the website
4.1.33A.(1) A person who is dissatisfied with a decision http://www.localgovernment.qld.gov.au/
made on an application to change the conditions
attached to an approval given under section 2.19(3)or For Infrastructure Charges Only
section 4.4 of the repealed Act may appeal to the court 4.1.36 Appeals about particular infrastructure
against- charges
(a) the decision; or (1) This section applies to a person who has been
given, and is dissatisfied with, an infrastructure charges
(b) a deemed refusal of the application. notice or a regulated State infrastructure charges notice.
(2) An appeal under subsection (1)(a) must be (2) The person may appeal to the court against the
started within 20 business days after the day notice of notice.
the decision is to be given to the person.
(3) The appeal must be started within 20 business days
(3) An appeal under subsection (1)(b) may be after-
started at any time after the last day a decision on the
matter should have been made. (a) if the notice is given because of a development
approval or master plan approval-the day the
Appeals against local laws applicant is given notice of the decision about the
4.1.33B.(1) An applicant who is dissatisfied with a approval; or
decision of a local government or the conditions applied (b) otherwise-the day the notice is given to the person.
under a local law about the use of premises or the
erection of a building or other structure permitted by the (4) An appeal under this section may only be about-
planning scheme may appeal to the court against the
(a) whether a charge in the notice is so unreasonable
decision or the conditions applied.
that no reasonable relevant local government, State
(2) The appeal must be started within 20 business infrastructure provider or coordinating agency could
days after the day notice of the decision is given to the have imposed it; or
applicant.
(b) an error in the calculation of the charge.
For Building Works Only (5) To remove any doubt, it is declared that an appeal
Rights of appeal conferred by Section 4.2.9 of the under this section can not be about the methodology
Integrated Planning Act 1997 as follows: used to establish the charge in the relevant
infrastructure charges schedule or regulated State
Division 3 – Appeals to tribunals relating to infrastructure charges schedule.
development applications
Appeals by applicants
2
Section 6.1.44 (Conditions may be changed or cancelled 3
by assessment manager or concurrence agency in certain Section 3.1.6 (Preliminary approval may override local
circumstances) planning instrument)
3 of 3
Used in these records
TPC 1469 - Change to Existing Approval (minor change to shade sails) [As Published]Related documentApplication case desk ↗
About this file
- File size
- 39 KB (small file)
- File type
No other editions are linked here.