Decision Notice DBW23 0050

of 4

Page text shows just the words. Original shows the document exactly as it was published.

                      Currency Period
               2.     This development approval lapses if the works have not substantially started by
                      27 June 2025, unless an application to extend the currency period is approved by Council.
                      Approved Plans
               3.     Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the table below.

                         Plan No.           Rev.   Plan/Document Name                            Date

                         1 of 15            B      Site Plan                                     23.05.23

                         5 of 15            B      Proposed Floor Plan (1 of 2)                  23.05.23

                         6 of 15            B      Proposed Floor Plan (2 of 2)                  23.05.23

                         9 of 15            B      Elevations (North & South)                    23.05.23

                         10 of 15           B      Elevations (West & East)                      23.05.23

                         11 of 15           B      Sections (Y-Y, X-X, W-W & Z-Z)                23.05.23

                      Building Height
               4.     The maximum height of the development must not exceed 8 metres above the ground level.
                      Car Parking
               5.     A minimum of 2 car parking spaces must be provided on site and made available and
                      accessible at all times for residents.
                      Environment
               6.     Sediment or any other material including building materials or waste products must not be
                      deposited or released into the road reserve, stormwater drain or adjacent properties.
                      Stormwater Drainage
               7.     Stormwater runoff from the development must be disposed of on-site without causing scour
                      or damage to the subject site or any adjoining property.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
               Infrastructure Charges
               1.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
               7.     PROPERTY NOTES

               Not applicable.




                                                                                                     Page 2 of 4
Document Set ID: 22477123
Version: 2, Version Date: 28/06/2023
Log in to download the original file

Decision Notice DBW23 0050.pdf · 143 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.