Project Management Plan
Attached to the e-mail Operational Works Application OPW21/0212 - 31 Bottlebrush Ave, - DA Form 1 - Civil & Landscaping Plans - Construction Management Plan - Qleave - Project Management Plan - Traffic Management Plan - cover letter.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn workers are agreeable.
Wind-affected plant, such as tower cranes, mobile cranes and hoists will not be permitted to operate where wind speeds exceed
those specified in:
The manufacturer’s instructions or operator’s manual; or
Any applicable Australian Standard, Code of Practice or WHSQ guidance material.
3.8.5 Working alone
The Principal Contractor
Remote or isolated work will be occurring on the work site and the following requirements will apply
has determined by risk
No remote or isolated work will need to occur on the work site
assessment that
Working alone on site Will not be permitted under any circumstances
Will not be permitted, with the following conditions
Working alone on site will not be permitted:
Unless it is not otherwise reasonably practicable (e.g. the subcontractor is a sole trader) and the Principal Contractor has given
the subcontractor permission to work alone
When undertaking any high risk construction work
When working at heights over 2 metres
When operating mobile plant
When working in a confined space
Unless the person is delivering materials to site
Unless the person is undertaking administrative or office work in the site offices
Other (provide details below)
Other (details)
NOTE: It is the subcontractor’s responsibility to ensure that any of their workers have access to a working mobile phone or
similar means of communication (e.g. two-way radio, pendant alarm) in the event of an emergency on site.
3.8.6 Fatigue
Management of fatigue is a regulatory requirement. When allocating staff to the project, subcontractors will be responsible for
ensuring that:
An adequate number of personnel are provided to complete the works in accordance with their contract and demands of the
building program;
Consideration is given to rest breaks, work hours and travelling times to and from site; and
Other factors that contribute to fatigue, such as the physical demands of the work, climate, work environment, lifting
equipment, storage and handling of materials, weight of loads, etc. are also considered.
3.9 Falling objects
The Principal Contractor will ensure the following equipment and administrative controls are provided to contain and minimise the
risk of falling objects
Catch platforms or nets
Containment screening (including perimeter screens)
Footpath closures
Heavy duty gantry
Hoardings
Road closures
Scaffolding (fully meshed)
Scaffolding (with kickboards or brick guards)
Temporary fencing
Tool lanyards
Other exclusion zones
Other (provide details below)
Other (details)
WHSMP-C 01/2018.8 Initials Page 16 of 39
____ ____