Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Scaffolding will be provided
   Around building perimeter
   In atrium areas
   For laying internal block walls
   Within the lift cores
   For access to basement levels
   For access to roof areas
   Within void areas
   In delivery areas for unloading trucks
   Other (provide details below)
Other (details)



3.11.4 Scaffolding supplied by subcontractor
The following requirements apply to scaffolding which is supplied by subcontractors.
Mobile scaffolds
Mobile scaffolding are in use                                                                      Yes     No
Unless by prior agreement with the principal contractor, the subcontractor will provide all mobile scaffolding required for their work.
       Mobile scaffolds must:
              Be erected in accordance with the manufacturer’s instructions and diagrams;
              Have internal access ladders if the work platform height is more than two metres;
              Have ladder hatches fitted, which are kept closed while the scaffold is in use;
              Not be used with split or offset work platforms unless:
                     The upper platform is being used exclusively for supporting tools and materials (not for working from); and
                     The difference in platform heights does not exceed 500mm.
                  Be fitted with kickboards if tools and materials are being used;
                  Not be erected to height that is greater than three times the smallest base width;
                  Be used on a firm level surface (not greater than five degree slope) and adjusted via the screw jacks to ensure the
                  work platform is level;
                  Have a minimum handrail height of 900mm;
                  Not to be moved whilst personnel are on the scaffold;
                  Have wheels/castors locked when in use;
                  Not be used near floor penetrations or slab edges unless protected with wheel stops (e.g. timber studs fixed around
                  edges); and
                  Be used at least three metres away from overhead power lines.

A-Frame trestle scaffolds
A-Frame trestle scaffolds are in use                                                               Yes     No
       Any A-Frame trestle scaffolds used on the project must:
              Be approved for use by the Principal Contractor beforehand;
              Only be used with a single plank if the plank height is less than two metres and is only being used for light work
              (painting, installing fascia and guttering, performing inspections and tests, etc.);
              Be a minimum of two planks wide for work over two metres, with planks properly secured with clamps;
              Have edge protection fitted along the length and ends of the platform where a person could fall two metres or more,
              or a lesser distance where a risk assessment identifies hazards that cannot otherwise be controlled (e.g. starter bars
              adjacent to scaffold). Note: This may include fitting edge protection along the internal face if the gap between the
              internal edge of the work platform and the face of the building exceeds 225mm);
              Be secured to prevent moving or toppling with ties or outriggers; and
              Not have a platform/plank height exceeding five metres.




WHSMP-C 01/2018.8                                               Initials                                                 Page 19 of 39

                                                  ____                         ____
Log in to download the original file

Project Management Plan.pdf · 350 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.