9.4.6 SUSTAINABLE BUILDING DESIGN CODE
Updated 03 August 2021
Noosa Plan, Version 1
Table 9.4.6.3 Criteria for assessable development
Performance Outcomes Acceptable Outcomes Response
Energy efficiency
PO1 No acceptable outcome provided Complies
Development minimises energy The development will include
consumption and the production skylights and voids to increase
of greenhouse gas emissions. natural light and minimise the
need for energy consumption.
Water efficiency and stormwater management
PO2 AO2.1 PO2 Complies
Development maximises water If for accommodation activities, a The development maximises
efficiency on site by minimum 3,000 litres of rain water water efficiency on site by
incorporating rainwater storage is provided per dwelling incorporating suitable measures
collection and reuse measures and reused for non-potable to manage stormwater for the
for non-potable purposes such purposes and incorporated into a development.
as irrigation. stormwater management plan for
the development.
AO2.2
With the exception of
accommodation activities, rain
water storage sufficient for the
intended use is captured and used
on-site for non-potable purposes
and incorporated into a stormwater
management plan for the
development.
Editor’s note—The Queensland
Development Code includes provisions for
the installation of rain water tanks and the
reuse of stormwater.
PO3 AO3.1 PO3 Complies
Sustainable Building Design Code
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Appendix E - Noosa Plan 2020 Assessment.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.