MCU19-0089_ICN.N1519_52-54 Mary St NOOSAVILLE

of 8

Page text shows just the words. Original shows the document exactly as it was published.

                                                         PO Box 141, Tewantin, QLD 4565
                                                         Phone (07) 5329 6500         Fax (07) 5329 6501
                                                         Email: [email protected] Website: www.noosa.qld.gov.au
                                                         ABN 97 969 214 121


     DECISION NOTICE ABOUT THE DECISION TO GIVE
         AN INFRASTRUCTURE CHARGES NOTICE
1.    PRELIMINARY

Infrastructure charges are triggered and issued on development approvals as a contribution towards the cost
of "trunk" infrastructure provided to service development and are governed by “Charges Resolutions” adopted
by local government in accordance with the planning legislation and regulations current at the time of issue.
Infrastructure Charges Notices are issued separately by both Council and Unitywater relating to their
specified “Trunk” infrastructure networks.


2.    THE DECISION AND REASONS FOR IT

The planning legislation provides for the following:
  a) authorises local governments to do either or both of the following for development approvals in relation
     to trunk infrastructure—
      (i) adopt, by resolution, charges for development infrastructure and levy the charges;
     (ii) impose particular conditions about development infrastructure; and
  b) authorises local governments, for non-trunk infrastructure, to impose particular conditions about
     development infrastructure; and
  c) provides for a regulation to govern local government adopted charges and charges by distributor-
     retailers under the SEQ Water Act for trunk infrastructure.
On 6 February 2014, Noosa Council adopted the "Noosa Shire Council Adopted Infrastructure Charges
Resolution (No.1) 2014" to replace the "Sunshine Coast Regional Council Adopted Infrastructure Charges
Resolution (No.4) 2011" that translated across to Noosa Council on 1 January 2014. The resolution has effect
on development approvals and charge notices issued from 6th February 2014 to 15 February 2015 in
accordance with the legislation current at the time of issue.
On 12 February 2015, Noosa Council adopted the "Noosa Shire Council Charges Resolution (No.2) 2014" to
replace the "Noosa Shire Council Adopted Infrastructure Charges Resolution (No.1) 2014" to include legislative
amendments that commenced on 4 June 2014. The resolution has effect on development approvals and charge
notices issued from 16th February 2015 to 27 October 2016 in accordance with the legislation current at
the time of issue.
On 20 October 2016, Noosa Council adopted the "Noosa Shire Council Charges Resolution (No.2) 2014
(Amendment 1)" to reflect adopted amendments made to the planning scheme. The resolution has effect on
development approvals and charge notices issued from 28th October 2016 to 23rd September 2018 in
accordance with the legislation current at the time of issue.
On 20 September 2018, Noosa Council adopted the "Noosa Shire Council Charges Resolution (No.3) 2018"
replacing the "Noosa Shire Council Charges Resolution (No.2) 2014 (Amendment 1)" to reflect the current
planning legislation, regulation and LGIP. The resolution has effect on development approvals and charge
notices issued from 24th to 22nd September 2018 in accordance with the legislation current at the time of
issue.
On 19 September 2019, Noosa Council adopted the "Noosa Shire Council Charges Resolution (No.4) 2019"
replacing the "Noosa Shire Council Charges Resolution (No.3) 2018 to reflect the Amendment of the Planning
Regulation 2017 where the prescribed amounts have been updated to the current 2019-2020 financial year
and Unitywater having adopted its own Infrastructure Charges Schedule to better comply with its respective
legislation, the “South-East Queensland Water (Distribution and Retail Restructuring) Act 2009” (SEQ Water
Act). The resolution has effect on development approvals and charge notices issued from 23th September
2019 in accordance with the legislation current at the time of issue.

                               PO Box 141              P. (07) 5329 6500    [email protected]
                               TEWANTIN QLD 4565       F. (07) 5329 6501    www.noosa.qld.gov.au         ICN - Page 4
Log in to download the original file

MCU19-0089_ICN.N1519_52-54 Mary St NOOSAVILLE.pdf · 642 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.