Original source · versioned page text
200917 La Mer Working Drawings - Rev #
Work in Progress
rev date issued details
client sign-off: date: Working Drawings
#-
WI 20.09.17 MS Working Drawings Rev#
P
legend
BAL# balustrade type
DR# drain type
FFL# finished floor level
FLF# floor finish type
HWD# timber type
MSC# miscellaneous item
MTL# metalwork type
REN# render finish
RET# retaining wall
SHR#
11,925 shower
STA# stair type
T# tile type
FHR# fire hose reel
refer to Materials and Finishes Schedule 1.2.1
and onwards for further detail/specs
NOTE: all structural elements; including all
slabs, columns, beams, footings and
framing; to be in accordance with structural
engineer's design and detail.
9,185
BAL01
RL 6,445 level 2 REN02 REN02
1,210
brass control join, as per
engineers drawings
SHR-01
RL 5,470 pool level 1 fall
100
REN01
new concrete stairs
finish: STA01
1,530
new security gate- refer
to schedules
noosa boardwalk
RL 3,885 new proposed path level
RL 3,490 ground level
existing stone wall
DR01
key plan 1:500
a: shop 5, 212 david low way, peregian beach, qld 4573
p: (07) 5471 3033 Alterations and Additions Scale 1:50
sparks architects www.sparksarchitects.com
37 Hastings Street, Noosa Heads La Mer Body Corporate 141 MS West Elevation WD 2.3
sparks architects pty. ltd. abn 89 124 611 721
qld architect's registration No. 3974 project client job no. drawn drawing dwg no.
GSPublisherVersion 166.6.74.18
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.