Attached to the e-mail Operational Works Application OPW20/0021- DA Form 1- Cover Letter - Engineering Plans - Owners Consent - 17 Cloudsley St Noosaville.
Chief Executive Officer Noosa Shire Council PO Box 141 Tewantin QLD 4565 19 January 2021 Attention: Development Services RE: 17 Cloudsley St, Noosaville (Lot 11 on RP64921) Council REF: DBW20/0014 - OPERATIONAL WORKS APPLICATION (Driveway Access) Please find enclosed an application for Operational Works Approval for the proposed driveway access to 17 Cloudsley St, Noosaville. Condition 11 of DBW20/0014 states: - “A sealed access driveway must be provided from Cloudsley Street to all parking and manoeuvring areas of the development. The works must be undertaken in accordance with an Operational Works approval and must include in particular: a. a driveway crossover in accordance with council standard drawings RS-049, RS-050 and respective addendums; b. a construction methodology that complies with the findings and recommendations of the report “Arborist Brief” for 17 Cloudsley St, dated July 2020 and prepared by Wayne Gooch of Tree Safe Australia Pty and included in Section 7 of this Decision Notice.” Enclosed is the following documentation for assessment of the application: - 1. DA Form 1 2. Owners consent 3. 360 Civil Consulting Engineering Drawings (2020036 Drawing No.’s 01 to 07) 4. Construction Methodology for driveway as required by Condition 11 part b of DBW20/0014 – outlined below Construction Methodology – Driveway Construction near Norfolk Pine The arborist report provided by Treesafe Australia dated July 2020 details that excavation or major fill and compaction over the trees root system needs to be minimised to ensure the preservation of the existing Norfolk Pine tree. Proposed construction methodology in the Norfolk Pine SRZ includes: - 1. Site arborist to supervise the installation of tree protection measures prior to any works occurring. 2. If pruning is required or instructed by the site arborist the tree contractor must have a minimum Level 3 AQS qualification in Arboriculture. 3. Topsoil strip to occur in the extent of the driveway area. 4. Crossover for the first 1.5m from invert of kerb is to be constructed of concrete.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 1 page
Page 2
5. Installation of porous / permeable paving material in accordance with manufacturer’s
specification and under inspection of the site arborist (as required). Extent of porous /
permeable paving material is to be in accordance with the approved OPW drawings.
6. Driveway extent between the property boundary and the garage is to be constructed of
concrete.
End of Driveway Construction Methodology.
This Operational Works design and documentation is considered to be generally in accordance with
the Noosa Planning Scheme.
We trust that the above information is acceptable and we look forward to working with Council to
achieve a satisfactory approval so that construction can commence on site as soon as practicable.
If you have any queries in relation to this application please do not hesitate to contact Beatrice
Gibberd on 0490 530 793.
Yours sincerely,
Beatrice Gibberd (RPEQ)
Director and Principal Engineer
360 Civil Consulting Pty Ltd