Skip to the record
Beware of cheap imitations.

Original source · versioned page text

Attachment A_R.A10342.002.00.Marine Plant MP

of 11

Page text shows just the words. Original shows the document exactly as it was published.

Dog Beach Sand Nourishment Project: Marine Plant Monitoring Plan                                           5
Monitoring Plan




2.2      Objectives
         The objective of this plan is to measure and evaluate the extent, condition and composition of live
         marine plants following construction of the beach nourishment works and to implement adaptive
         measures and/or corrective actions, as required, to ensure living marine plants in the disturbance
         area are consistent with pre-construction conditions or better.

         Refer to Noosa Spit Coastal Protection Environmental Assessment for pre-construction marine plant
         conditions within the study site (BMT 6th January 2021: R.A1032.002.00_Environmental
         Assessment.docx).

2.3      Responsibilities and Obligations
         Noosa Shire Council is responsible for implementing and reporting on this plan.

2.4      Qualifications
         Monitoring and associated reporting shall be performed by a qualified ecologist with experience in
         marine plant and fisheries habitat site assessments in south-east Queensland.

2.5      Timing
         The monitoring schedule will consist of the following site surveys:

         • A post construction monitoring survey within two months of construction completion

         • Survey conducted six months after the post-construction survey

         • Yearly for a period of three years after completion of the works.

         Program timing may be adjusted in the event adaptive management measures and/ or corrective
         actions are required.

         The monitoring programme can conclude after a period of three years following completion of the
         works and once it is demonstrated there is no, to very low, potential for long-term impacts on living
         marine plants associated with sand nourishment. Conclusion of the program shall be approved by
         the Queensland Department of Agriculture and Fisheries (DAF).

2.6      Monitoring
         Monitoring assessments of the study site will be undertaken by a suitably qualified ecologist to
         measure and evaluate live marine plants and fisheries resources following construction and to
         identify any potential management issues.

         Site record sheets and permanently established photo monitoring points will be used for recording
         and monitoring marine plant condition. The assessment will involve traverses of the entire study site
         to describe and map the presence of land-based marine plant communities and evidence of
         associated fisheries habitat values. Site data will be recorded at representative locations and will
         include:

         • Photographs at established monitoring points



G:\admin-share\Admin\A10342.g.mpb.NoosaSpitSEMPdesign\R.A10342.002.00.Marine Plant
MP.docx
Log in to download the original file

Attachment A_R.A10342.002.00.Marine Plant MP.pdf · 729 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.