Application Report

of 157

Page text shows just the words. Original shows the document exactly as it was published.

RECONFIGURATION OF A LOT (1 INTO 5 LOTS)
83 BUTLER STREET, TEWANTIN



 PERFORMANCE OUTCOMES                      ACCEPTABLE OUTCOMES                               PROPOSAL                                      COMPLIANCE
                                           AO8.3                                             AO8.3                                         ☐Compliant
                                           Vegetated     stormwater     management           The proposal does not involve stormwater      ☒N/A
                                           systems to be dedicated as public assets are      management systems to be dedicated as
                                                                                                                                           ☐Performance Solution
                                           established and maintained during the             public assets.
                                           maintenance period to ensure optimal
                                           vegetated growth and that the functional
                                           elements of the system achieve the design
                                           function at the end of the maintenance
                                           period.
 PO9                                       AO9.1                                             AO9.1                                         ☒Compliant
 Treatment systems are designed to         Free draining inlets and outlets are provided     The proposal provides a suitable stormwater   ☐N/A
 eliminate or minimise health, safety      to ensure that waters do not pond for more        management system as identified in the
                                                                                                                                           ☐Performance Solution
 and aesthetic hazards, including risks    than 24 hours.                                    attached Civil Engineering Report.
 associated with      insect breeding,
 odour and public safety.
                                           AO9.2                                             AO9.2                                         ☒Compliant
                                           Developments are designed to eliminate            The proposal provides a suitable stormwater   ☐N/A
                                           retaining walls in excess of 0.8m for any         management system as identified in the
                                                                                                                                           ☐Performance Solution
                                           water quality treatment device.                   attached Civil Engineering Report.


 Hydrology and waterway stability          AO10                                              AO10                                          ☒Compliant
 PO10                                      The development is designed to:          The proposal provides a suitable stormwater            ☐N/A
 Development prevents increased bed        a) limit the peak 1 year ARI event management system as identified in the                       ☐Performance Solution
 and bank erosion and sedimentation in        discharge    within   the   receiving attached Civil Engineering Report.
 receiving waterways by avoiding              waterway to the pre-development peak
 changes in low rate, peak flow run-off       1 year discharge;
 and flow duration.




                                                   BRISBANE: P +617 3361 9999 I 57 Manilla Street, EAST BRISBANE Q 4169
                                               NORTHERN NSW: P +61 2 6637 9110 I Building 1, 1 Porter Street, BYRON BAY N 2481
                                                            E: [email protected] W: www.tpalliance.com.au
Log in to download the original file

Application Report.pdf · 2.0 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.