Skip to the record
Mmm.. taste the original NoosaWatch™

Original source · versioned page text

2015-04-28 Infrastructure & Services Committee Agenda

of 100

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (10.4 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA                                      28 APRIL 2015


To date, management intervention has included:
   Removal of the rope swings which commenced in November and has continued on an
     ongoing basis.
   Received from the Department of Agriculture, Fisheries, Forestry (DAFF), the list of design
     constraints for a recreational/fishing structure to be constructed within a Management Level
     A classification of a declared Fish Habitat Area.
   Outsourced quotes for the structure design from consultants (e.g. Request for Quote) which
     included the design constraints from DAFF.
   Received one quote for design of the recreational/fishing structure (one consultant declined
     to quote and one consultant withdrew their quote).
   Developed and distributed a Project News factsheet around the Weyba Creek Esplanade
     residential area.
   Visited three Noosa Backpacker establishments to inform management about the
     environmental and public risk concerns at Weyba Creek rope swing area and the intended
     management intervention. The backpacker establishments indicated they would no longer
     send their guests to the area.
   Conducted a Community Information Session onsite to discuss design of the
     recreational/fishing structure and glean feedback from local residents.

Finance & Risk

The current funding for this project is split between two financial years as follows:
 2014/15, $20,000 for design
 2015/16, $200,000 for construction.
Based on the estimated costs of Option 2 a revision of the funding from $200,000 to $120,000 for
2015/16 will be required as part of the 2015/16 Budget development.

The total costs of a formal access to Weyba Creek at the picnic table location by way of steps to
the creek and a canoe/kayak launch for recreational purposes (see photo of timber example
below) is estimated to be $100,000 ($80,000 for an aluminium structure) plus the associated
costs of bank stabilisation measures (i.e. site preparation, planting, fencing, signage and
monitoring) at the former rope swing area are estimated to be $20,000.




                                                                                        Page 55 of 100
Log in to download the original file

2015-04-28 Infrastructure & Services Committee Agenda(PDF, 10MB).pdf · 10.4 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.