6.3.2        Temporary and Permanent Retention Systems
Given that the planned basement footprint extends close to all of the site boundaries, excavations will
cover nearly the full available site area. Allowing for the footprint extents some form of temporary
shoring will be required to support the excavations. Suitable shoring methods for the ground conditions
encountered could include sheet pile and secant (over-lapping) piles. It is understood that secant piles
are proposed for this project.
Sheet piles could also be considered, however, the flexibility of a sheet pile shoring wall and vibration
associated with construction may put adjacent structures at risk from settlement and so a secant wall is
planned. Unitywater and NC requirements for existing infrastructure may also restrict the use of sheet
piles.
Temporary shoring should penetrate into the underlying dense (or denser) indurated sands/coffee rock,
to minimise flows up through the base of the excavation. Deeper ‘key in depths’ may be required,
depending on detailed design of the temporary shoring system. Care would need to be taken with
shoring to manage potential vibration impacts on nearby structures. It would be prudent to conduct a
dilapidation survey of such adjacent structures prior to commencement of the site works.
Considering the potential for adverse impacts on nearby structures due to settlement, and potential
environmental impacts due to significant dewatering of the groundwater table; the proposed temporary
retention system should be designed to support at least partial hydrostatic pressure. Given our
observations of groundwater levels and ASS conditions, we recommend that the external groundwater
level should not be dewatered deeper than 1.5 m BGL.
An internal dewatering system (e.g. a series of sand spears or wells connected to an extraction pump) will
likely be required to pick up any seepage that migrates through the shoring system, and up through the
sands across the basement excavation floor. This would be to prevent ‘boiling’ of the basement
subgrade. It should be possible to manage the groundwater extraction system such that the impact on
the surrounding, external groundwater table is negligible. To minimise the volumes of extracted
groundwater and the associated treatment requirements, it would be prudent to adjust the depths of
wells/spears and pumping rates such that the stabilised groundwater level below the excavation floor is
optimised (i.e. dewatering is not carried out to an excessive depth).
To minimise inflow rates and reduce the risk of external dewatering care must be taken to ensure the
temporary shoring wall is ‘water-tight’. Special attention would need given to the detailing such as
ensuring secant piles overlap or using interlocking sheet piles (with a ‘clutch’ system) as opposed to
overlapping sheets which leak.
Subject to the recommendations outlined above, negligible impacts are anticipated on surrounding
buildings and infrastructure due to the following:
   Temporary retention will be utilised around the entire excavation perimeter.
   External dewatering will not be undertaken below 1.5 m BGL, with the internal dewatering system
    optimised such that dewatering is not undertaken to an excessive depth.
   The upper soil layers primarily consist of sands, and groundwater levels are expected to fluctuate in
    response to weather conditions and tidal cycles. As such, the internal dewatering system is not
    anticipated to cause significant changes in the surrounding groundwater levels or induce soil
    shrinkage or swelling.
Due to the relatively shallow depth that groundwater was encountered during the investigation, the
proposed basement will need to be designed as a ‘tanked’ structure. The design of the proposed


Geo-environmental Investigation Proposed Residence
11 March 2025 | 25040-001-Rev0                                                                              13

Used in these records

About this file

File size
12.4 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Geo-environmental Investigation.pdf · 12.4 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.