NOOSA COUNCIL IDAS Development Application Decision Notice                                                        4 of 7


       10.2. Disposal for firewood.

       10.3. Disposal for landscaping purposes.

       10.4. Transport to alternative site for breaking down materials provided that all necessary permits have
             been obtained to allow the alternate site to be used for this purpose.

       10.5. The Applicant is advised that other methods may be considered provided full details of the method
             are submitted.

       10.6. The applicant is advised that burning off in an unacceptable method of disposal.

11.    Security in the form of a cash bond or trading bank guarantee to the sum of $5,000 must be submitted, to
       secure performance of all conditions of this approval, prior to the issue of a Development Permit for
       building works. The cash bond or trading bank guarantee will be returned on performance of the
       conditions of approval less any costs incurred by Council in respect of enforcing performance of this
       permit.

12.    Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are not
       constructed under overhead electricity transmission lines, or within any easements.

13.    A geotechnical report, prepared by a registered professional engineer shall be obtained, and it should
       either:-

       13.1. certify that the site is not at risk from landslide emanating from the site or from other land; or

       13.2. identify methods of stabilising all buildings, accessways and uses areas; and where the
             geotechnical report identifies methods of stabilising buildings, accessways and uses areas. The
             development shall implement those methods, which are recommended.

14.    Sediment and erosion control measures must be in place prior to the construction of the house. If such
       measures are not in place or are not satisfactory, ‘on the spot’ fines may be issued. Such fines can be
       issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater
       system or natural waterways.

15.    The Development Permit for a material change of use lapses if the use has not happened by 3 May 2011,
       unless an application to extend the currency is approved by Council.




MSOffice c:\docume~1\shesse\locals~1\temp\bcl technologies\easypdf 5\@bcl@600d3cb5\@[email protected]

Used in these records

About this file

File size
34 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_642 - COMPILED Decision Notice [As Published].pdf · 34 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.