1. INTRODUCTION
Bitzios Consulting Pty Ltd (Bitzios) has been commissioned by Rubicon Design and Construct Pty Ltd
(Rubicon) to provide traffic engineering advice in relation to a proposed expansion of the existing Noosa-
Tewantin RSL (RSL), located at 5 Memorial Avenue, Tewantin (Lot 10 on SP273411).
1.1 DEVELOPMENT DETAILS
Table 1.1 provides a summary of the existing and proposed total use area (TUA) during each stage of the
proposed expansion, as well as the corresponding on-site car parking provision.
Table 1.1: Proposed Development
Stage Total Use Area Total On-Site Parking Provision
Existing 1,957.84m² 86 spaces
Stage 4 Expansion 2,549.61 (+591.77m²) 124 (+38 spaces)
Stage 5 Expansion 2,620.21 (+662.37m²) 123 (+37 spaces)
Stage 6 Expansion 2,898.11 (+940.27m²) 123 (+37 spaces)
Relatively Increase 48% increase in Total Use Area 43% increase in Total On-site Parking
A copy of the proposed development plans is included at Appendix A.
1.2 BACKGROUND
A pre-lodgement meeting was held with Noosa Shire Council (Council) on 31st May 2016, to discuss the
proposed development. Key traffic related items discussed at the meeting are summarised below:
“Parking shortfalls are undesirable when combined with the proposal’s built form and landscaping
relaxations. A traffic report could assess demand for the existing RSL over an extended period to
demonstrate parking demands.
Council has the following engineering concerns with the submitted plans:
demonstrating that there is no or minimum loss of on-street parking spaces;
the ability for heavy vehicles (delivery/service/waste) to enter the site in a forward gear, access the
servicing areas and exit the site in a forward gear; and
the layout includes the necessary dedicated delivery/service/waste areas.”
A copy of the pre-lodgement meeting minutes is included at Appendix B.
1.3 SCOPE OF ASSESSMENT
The following scope of works has been completed in preparing this report:
undertaking a site inspection to review existing traffic and parking conditions and club operations;
attending a pre-lodgement meeting with Council to discuss the proposed development;
reviewing the proposed site layout against relevant Council requirements and Australian Standards;
obtaining traffic survey data to determine existing volumes on the surrounding road network;
obtaining parking occupancy data for the club and road network fronting the subject site;
consideration of potential development impacts at the Memorial Avenue/Doonella Street roundabout;
reviewing the site access locations and forms in accordance with Council guidelines;
interpolated off-street parking requirements for the expansion based on parking occupancy data;
reviewing the internal parking layout in accordance with Council and Australian Standards;
reviewing methods and facilities for on-site servicing including swept path analysis; and
reviewing active and public transport network connectivity in proximity to the subject site.
Project No: P2623 Version: 002 Page 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (MCU16_0079 Appendix E - Traffic Impact Assessment.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.