ORDINARY MEETING AGENDA 19 JANUARY 2017
b. be undertaken in compliance with the provisions of Australian Standard
AS3798: Guidelines on Earthworks for Commercial and Residential
Developments
c. all fill and associated batters must be contained entirely within the subject
site unless written permission from the respective landowner(s) is provided
to Council.
15. All Earthworks and construction works must be carried out taking into
consideration the protection of any existing above and below surface services,
and the stability and protection of fences and any buildings and structures on the
adjoining properties.
Site Access and Driveways
16. Sealed access driveways must be provided from Taylor Court to all parking and
manoeuvring areas of the development generally in accordance with the
approved plans. The works must be undertaken in compliance with an
Operational Works approval and must include in particular:
a. a driveway crossover generally in accordance with the approved plans and
standard drawing SEQ R-051 with a width not exceeding 9.0m at the
boundary line
b. traffic restriction signage to identify Exit Only and Entry Only requirement
in accordance with approved plans
c. grades and configuration that demonstrate smooth maneuvering and
adequate ground clearance (no bottoming down) for for all vehicles and
particularly for fuel tankers, articulated vehicles, heavy rigid vehicles along
the vehicles traveling paths
d. finished levels and grades to match the existing concrete pathway along
the frontage of the site
e. any landscaping, retaining walls, fences and fixtures near the access entry
point must comply with AS 2890.1 requirements for sight visibility for
pedestrians and cyclists at driveways
f. adjustment to any affected utility services in accordance with the
requirements of the relevant service provider.
Car Parking
17. A minimum of 33 car parking spaces and 4 motor cycle spaces must be provided
and marked on the site generally in accordance with the approved plans and in
compliance with Australian Standard AS2890: Parking Facilities for User Class
3A Table1.1. The works must be undertaken in accordance with an Operational
Works approval and must include in one (1) disabled parking space within the
total.
18. All car parking areas and access driveways must be maintained exclusively for
vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
19. Prior to the submission of any Operational Works Application, the applicant must
provide a Traffic Management Plan for the refueling procedure that demonstrates
no adverse impact on traffic movements in Taylor Court or on the internal traffic
within the site. The plan should include any necessary time restrictions to be
implemented on refueling operation schedules to address the potential of
adverse impact on traffic.
20. All driveways, cars, motor cycles and bicycles parking areas must be line marked
in accordance with approved plan/s.
Page 7 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.