2019-12-11 SM Agenda - Item 1 - Attachment 7 - Final New Noosa Plan - Part 8-10 Schedule Appendix - Clean version

of 439

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (23.3 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Performance Outcomes                                                    Acceptable Outcomes
PO22
Fixed floating structures whether or not attached to land (e.g.         No acceptable outcome provided
pontoons and any associated walkways) and boat ramps are not
located within the Noosa Waters Estate.


Flooding and amenity functions                    Table 9.4.11.3 Criteria for assessment (part)
Performance Outcomes                                                    Acceptable Outcomes
Flooding and amenity functions ­ operational works within Noosa Waters Estate waterways
PO23                                                                    AO23.1
The flood detention and amenity functions of the area adjacent to       For premises adjoining a waterway within the Noosa Water
the revetment wall within Noosa Waters Estate are retained and          estate, no building work, filling or excavation works within 4.5
enhanced by ensuring—                                                   metres of the centre line of the top of the concrete revetment wall.
(a)   works do not protrude through a batter line of 1:4.5
      measured from the centre line of the revetment wall;              AO23.2
                                                                        A minimum of 25% of the area within 4.5 metres of the revetment
(b)   there is no additional load placed on the revetment wall;
                                                                        wall is planted with shrubs and small trees with a mature height
(c)   works do not pose a risk to the membrane adjoining the            of 3 metres or less.
      revetment wall;
(d)   amenity of the waterway and surrounding land uses is not          AO23.3
      adversely affected by development (building, filling or           The ground surface within the first metre of the revetment wall—
      excavation) ensuring—                                             (a)   is grass or ground cover; and
      (i)     the 4.5 metre setback area is predominantly soft          (b)   does not include shrubs.
              landscaping;
      (ii)    a maximum of 25% of the area is impervious;               AO23.4
      (iii)   dominant impervious areas and masonry retaining           Side boundary fences within 4.5 metres of the revetment wall
              walls are avoided;                                        taper down to a maximum height of 1.2 metres at the revetment
                                                                        wall and no more than 1.5 metres at a distance of 2.25 metres
      (iv)    retaining structures and the like are light weight, low   from the revetment wall.
              rise and screened by landscaping;
      (v)     natural materials such as timber or rock are used
              rather than manufactured materials;
      (vi)    the acoustic privacy and access to sunlight of
              surrounding development is protected; and
      (vii)   views are not impeded.

PO24
No shore side anchor points are installed within 4.5 metres of the No acceptable outcome provided
centre line of the revetment wall.
PO25
No mooring, anchoring, tying or docking of vessels occurs               No acceptable outcome provided
adjacent to the revetment wall.

Figure 9.4.9.3A & 9.4.9.3B
Character & Amenity
FIGURE 9.4.9.3A                                                                                  FIGURE 9.4.9.3B




  **FINAL DRAFT ­ Post Consultation 2019**
                                                                                                                                 Page 10 of 16
Log in to download the original file

2019-12-11 SM Agenda - Item 1 - Attachment 7 - Final New Noosa Plan - Part 8-10 Schedule Appendix - Clean version(PDF, 22MB).pdf · 23.3 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.