Quarry Rehabilitation
Lake Macdonald Drive, Lake Macdonald
© 2012 - TTM Consulting (SC) Pty Ltd Reference No: 12SCT0037
7.4 Internal Site Access Review
7.4.1 Internal Parking and Manoeuvring
TTM understands that a dedicated on-site compound will be established, which will provide
dedicated parking for up to 5 vehicles and adequate turning areas for truck activity.
7.4.2 Bridge Structures
TTM understands that the established creek crossing structure(s) along the Westridge Quarry
access have been designed to cater for the predicted development truck loads. TTM anticipates
that the structures will adequately cater for the development demands; however, a further
inspection by a structural engineer may be warranted.
Page | 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.