planning report - 20 kauri · MCU23/0109
4.4 Car parking
The Driveways and Parking Code (AO6.1) requires 1 space per small dwelling and 1 space per 4
dwellings (or part thereof) for onsite parking. This results in 10 covered spaces and 2.5 spaces 12.5
spaces in total. The proposal is providing 1 covered space per dwelling, 2 visitor bays and 2
motorcycle bays.
4.5 Works Codes
The site would be connected to essential urban services including reticulated sewer, water, electricity
and NBN. A SWMP is provided which indicates under driveway detention / storage at towards the
southern part of the site to provide water quality in accordance with relevant standards.
While there are some moderate cuts required, it is well below the acceptable outcome of 1.5 metres.
Fill has been kept to a minimum, with a retaining wall proposed along the northern boundary at a
height between 0.05-1.25. Although this retaining wall is located on the boundary, the majority of
the wall is below 1 metre. An erosion and sediment control plan has been provided to ensure no
environmental damage occurs during construction phase.
New tree species will be planted along the boundaries and between buildings to complement and
soften the built form. Turning paths are provided and demonstrate that vehicles can enter and exit
the site in a forward gear. Two (2) bin enclosure areas are also provided for recycle and general
waste ensuring waste collection and recycling can be in accordance with the Code. Residents are
responsible for kerb side collection, consistent with similar developments adjoining and nearby in
Kauri Street.
4.6 Sustainable Building Design Code
The design allows for natural light and ventilation to make the most of the prevailing breezes. The
lower level has a ceiling height of 2.85m and the upper level 2.55m. The open floorplan allows for
cross ventilation on both levels of each townhouse. The living spaces face north or east where
practicable ensuring maximum dwelling yield and efficient use of the lot shape in accordance with
the planning scheme.
The stormwater water management plan also includes stormwater detention tanks and a bioretention
area to the southwest corner of the site. Building products are to be ethically and efficiently sourced
and waste kept to a minimum to ensure cost efficient and less waste in the building process.
Page 11 of 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
planning report - 20 kauri.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.6 MB (small file)
- File type
No other editions are linked here.