70. All building materials containing asbestos products are wrapped and disposed of in
accordance with the Public Health Regulation 2006 and the Environmental Protection
Regulation 2008.
Note: Asbestos is a Regulated Waste. The Department of Environment & Science licenses
businesses that transport asbestos waste, and landfills that accept this waste.
71. All building materials containing asbestos, including asbestos cement sheeting or roofing and
lagging are removed from the building prior to demolition/relocation.
Plumbing and Drainage
72. It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2003’ that at
demolition of a building, the existing sanitary drain upstream from the connection point for a
service provider’s sewerage system must be sealed water tight. This work is deemed as
notifiable Work and must be carried out by a suitably licenced plumber who must submit an
As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
Construction Commission) within 10 days of completing the work.
Additional Conditions – MCU19/0049.01 – 16 June 2026
PRIOR TO COMMENCEMENT OF WORKS (INSTALLATION OF FIRE PUMP)
73. Prior to the commencement of any works on site, an Arborist Report must be prepared by a
suitably qualified person.* The report must identify all trees to be retained as shown on the
approved plans and outline detailed tree protection measures in accordance with AS
4970:2025 Protection of Trees on Development Sites.
*(Refer to Advisory Note)
74. Tree protection fencing must be installed under the supervision suitably qualified person.*
(Refer to Retention of Existing Trees Conditions)
DURING CONSTRUCTION (INSTALLATION OF FIRE PUMP)
Retention of Existing Trees
75. All trees and vegetation identified for retention must be protected in accordance with AS
4970, Protection of trees on development sites.
76. A qualified person * must be engaged for the duration of the works to:
a. Ensure tree measures are installed and maintained during construction in accordance
with AS 4970, Protection of trees on development sites and an Arborist Report,
prepared by suitably qualified person.*
b. Oversee installation of all tree protection fencing prior to commencement of any works
onsite (including any clearing and earthworks).
c. Supervise tree protection within the development site and frontages, prior to, during
and following construction in accordance with AS 4970, Protection of trees on
development sites.
d. Oversee approved tree removal in proximity to retained trees
*(Refer to Advisory Note)
5. REFERRAL AGENCIES
Not applicable.
Page 11 of 16
Document Set ID: 24873125
Version: 4, Version Date: 18/06/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval - MCU19 0049 01 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 211 KB (small file)
- File type
No other editions are linked here.