Information Response MCU12/0208

of 64

Text shows just the words. Original shows the document exactly as it was published.

conditions as part of any Preliminary Approval in order to guide the design of the future road network.

Issue
An off-road shared path exists on the western side of the Walter Hay Drive bridge over Eenie Creek to
the north of the proposed development. However, no pathway connection to this is proposed.

Information Required

66      Demonstrate how off-road pedestrian / cycle pathway access can be provided safely and efficiently
        between the development and the existing off-road shared path on the western side of the Walter
        Hay Drive bridge over Eenie Creek.

Response:

Please refer to Attachment 3 which incorporates the A1 Concept Master Plan, this document outlines an
indicative off road pedestrian and cycle pathway network that connects to the existing off-road shared path on
the western side of the Walter Hay Drive bridge over Eenie Creek.

Issue
Planning Horizon

It is understood from the application material that construction of the various development components is
intended to be staged over a number of years.

Information Required

67      The traffic planning horizon adopted should be ten years after the completion of the construction in
        accordance with normal practice.

Response:

The traffic assessment included in the amended Traffic Assessment Report in Attachment 14 has accounted for
2018 year of opening, and 2028 ten year design horizon, as explained at Section 5.2.

Issue
Travel Times on Walter Hay Drive

The travel time estimates included in the TIA are based on current traffic volumes and operating conditions,
except for some provision for activation of the southern Noosa Business Centre access intersection. No
assessment has been made of impacts in respect of future travel times (up to the planning horizon). This
is particularly relevant because traffic volumes are expected to increase more quickly on Walter Hay Drive
than on Eumundi Road, and the proposed site access roundabout is estimated to be the most congested
roundabout in the relevant network south of Eenie Creek.

Information Required

68     Provide assessments for future year operations.

Response:

Please refer to Section 3.2 of the amended Traffic Assessment Report for a brief summary of the access options
analysis, with the comprehensive report included in Appendix G of the report. Additionally an analysis of travel
time delays is included at Section 5.3 of the amended Traffic Assessment Report.

Issue
External Road Network Connectivity
                                                     48

Used in these records

About this file

File size
1.6 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Information Response MCU12_0208.pdf · 1.6 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.