PEREGIAN BEACH ACTIVE STREET - STAGE 1 PROGRESS UPDATE AND NEXT STEPS (Deferred from the General Committee Meeting dated 16 March 2026) · Attachment 8 - Project Program - Peregian Active Street
Attachment 8 - Project Program - Peregian Active Street
ID Task Task Name Duration Start Finish Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027
Mode M J J A S O N D J F M A M J J A S O N D J F M A M J
1 Design & 163 days Mon 22/09/25 Wed 27/05/26 27/05
Procurement
2 Instruct ADG to 25 days Mon 22/09/25 Mon 27/10/25
issue a 90% design
(variation to
scope)
3 Creation of 15 days Tue 28/10/25 Mon 17/11/25
Illustrative Design
4 Councillor Briefing 1 day Thu 27/11/25 Thu 27/11/25
on 90%
5 Makeup councillor 1 day Tue 9/12/25 Tue 9/12/25
briefing
6 Webpage Update 1 day Thu 18/12/25 Thu 18/12/25
& 90% Design
7 1:1 with affected 28 days Mon 12/01/26 Thu 19/02/26
residents
8 Pop up 1 1 day Wed 21/01/26 Wed 21/01/26
9 Pop up 2 1 day Tue 27/01/26 Tue 27/01/26
10 Walkshop 1 day Wed 18/02/26 Wed 18/02/26
11 Feedback 26 days Tue 20/01/26 Wed 25/02/26
Collation
12 Council S&O 1 day Tue 10/03/26 Tue 10/03/26
Reporting
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Program v3
Summary Manual Summary Rollup Progress
Date: Thu 26/02/26
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 2 pages
Page 2
ID Task Task Name Duration Start Finish Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027
Mode M J J A S O N D J F M A M J J A S O N D J F M A M J
13 Council General 1 day Mon 16/03/26 Mon 16/03/26
Committee
14 Council Ordinary 1 day Thu 19/03/26 Thu 19/03/26
Meeting
15 ADG Issue for 50 days Mon 15/12/25 Mon 9/03/26
tender
16 Prepare for 21 days Mon 23/02/26 Mon 23/03/26
Tender
17 Release to 20 days Tue 24/03/26 Wed 22/04/26
VendorPanel
18 IFC 15 days Tue 10/03/26 Mon 30/03/26
19 Evaluation 5 days Thu 23/04/26 Wed 29/04/26
20 Report to Council 18 days Thu 30/04/26 Tue 26/05/26
21 Award Tender 1 day Wed 27/05/26 Wed 27/05/26
22 Delivery 211 days Thu 28/05/26 Wed 7/04/27
23 Documentation 10 days Thu 28/05/26 Wed 10/06/26
24 Pre-Start Meeting 1 day Thu 28/05/26 Thu 28/05/26
25 Site Mobilisation 1 day Thu 11/06/26 Thu 11/06/26
26 Construction 200 days Fri 12/06/26 Wed 7/04/27
27 Handover 15 days Thu 8/04/27 Wed 28/04/27
28 PC Walkthrough 1 day Thu 8/04/27 Thu 8/04/27
29 Ommisions & 10 days Fri 9/04/27 Thu 22/04/27
Defect
Rectifications
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Program v3
Summary Manual Summary Rollup Progress
Date: Thu 26/02/26
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 2
Page 3
ID Task Task Name Duration Start Finish Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027
Mode M J J A S O N D J F M A M J J A S O N D J F M A M J
30 PC 0 days Thu 22/04/27 Thu 22/04/27 22/04
31 Documentation 15 days Thu 8/04/27 Wed 28/04/27
Handover
32 Grant Funding 15 days Thu 29/04/27 Thu 20/05/27
Completion
33 Finalise 15 days Thu 29/04/27 Thu 20/05/27
Completion
Documentation
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Program v3
Summary Manual Summary Rollup Progress
Date: Thu 26/02/26
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 3