PEREGIAN BEACH ACTIVE STREET - STAGE 1 PROGRESS UPDATE AND NEXT STEPS (Deferred from the General Committee Meeting dated 16 March 2026) · Attachment 8 - Project Program - Peregian Active Street
ID Task Task Name Duration Start Finish Half 2, 2025 Half 1, 2026 Half 2, 2026 Half 1, 2027
Mode M J J A S O N D J F M A M J J A S O N D J F M A M J
30 PC 0 days Thu 22/04/27 Thu 22/04/27 22/04
31 Documentation 15 days Thu 8/04/27 Wed 28/04/27
Handover
32 Grant Funding 15 days Thu 29/04/27 Thu 20/05/27
Completion
33 Finalise 15 days Thu 29/04/27 Thu 20/05/27
Completion
Documentation
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: Program v3
Summary Manual Summary Rollup Progress
Date: Thu 26/02/26
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 3