                      Infrastructure Charges
               3.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
                      Building and Construction Industry (Portable Long Service Leave) Levy
               4.     The QLeave levy must be paid prior to the issue of a development permit where it is required.
                      Council will not be able to issue a Decision Notice without receipt of details that the Levy has
                      been paid.
                      Preparation of a Preliminary Construction Management Plan
               5.     A preliminary Construction Management Plan must be submitted with the Operational Works
                      application and must address the following:
                      a.      Traffic management during all phases of construction;
                      b.      Adequate parking arrangements for works and deliveries;
                      c.      appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD); and
                      d.      provision for safe vehicle and pedestrian access across the frontage of the site both
                              during daily construction and after daily construction has ceased.
               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required               Subject of the required Development Permit

                Development Permit for Operational Works          Vehicle crossover

                Development Permit for Building Works             All building work.

               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.




                                                                                                      Page 15 of 15

Document Set ID: 24750347
Version: 9, Version Date: 08/07/2026


[OCR of page images]
Infrastructure Charges

3. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue. For
further information, please refer to https://www.noosa.qid.gov.au/planning-
development/development-tools-guidelines/infrastructure-charges

 

Building and Construction Industry (Portable Long Service Leave) Levy

4. | The QLeave levy must be paid prior to the issue of a development permit where it is required.
Council will not be able to issue a Decision Notice without receipt of details that the Levy has
been paid.

Preparation of a Preliminary Construction Management Plan

5. — Apreliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:

a. Traffic management during all phases of construction;
b. | Adequate parking arrangements for works and deliveries;

Cc. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD); and

d. provision for safe vehicle and pedestrian access across the frontage of the site both
during daily construction and after daily construction has ceased.

8. PROPERTY NOTES

Not applicable.

9. VARIATION APPROVAL DETAILS

Not applicable.

10. FURTHER DEVELOPMENT PERMITS REQUIRED

Type of Development Permit Required Subject of the required Development Permit

Development Permit for Operational Works _ Vehicle crossover
Development Permit for Building Works All building work.

11. SUBMISSIONS
Not applicable.
12. RIGHTS OF APPEAL

You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.

During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.

13. OTHER DETAILS

If you wish to obtain more information about the decision, electronic copies are available online at
www.noosa.qld.gov.au or at Council Offices.

Page 15 of 15

Document Set ID: 24750347
Version: 9, Version Date: 08/07/2026

Used in these records

About this file

File size
6.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning MCU26 0010 (As Published).pdf · 6.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.