Skip to the record
Accept no substitutions.

Original source · versioned page text

PEREGIAN BEACH ACTIVE STREET - STAGE 1 PROGRESS UPDATE AND NEXT STEPS (Deferred from the General Committee Meeting dated 16 March 2026) · Report

of 16

Page text shows just the words. Original shows the document exactly as it was published.

ORDINARY MEETING                                                                     19 MARCH 2026


at key locations.

Ordinary Meeting Minutes 19 December 2019
That Council note the report by the Infrastructure Planning, Design and Delivery Manager to the
Services & Organisation Committee Meeting dated 10 December 2019 and appoint the following
three Councillors, Cr Wellington, Cr Stockwell and Cr Wilkie as members of Noosa Cycling & Walking
Strategy and Highest Priority Cycling Corridors – Project Control Group (PCG).

Ordinary Meeting Minutes 20 February 2020
PETITION: REQUEST COUNCIL TO IMPROVE THE SAFETY AND AMENITY OF PITTA STREET,
PEREGIAN BEACH
That the petition tabled by Cr Wellington requesting that Council improve the safety and amenity of
Pitta Street, Peregian Beach with regards to parking and pedestrian access be received and referred
to the Chief Executive Officer to determine appropriate action.


Finance
The project is 100% Grant funded through the South East Queensland Livability Fund and the Active
Transport Fund.
Current project budget breakdown:
Funding Mechanism24/25FY           25/26FY           26/27FY            Total
SEQ Liveability        $80,120     $516,548          $283,332           $880,000
ATF                    $0          $501,668          $283,332           $785,000
Noosa Council          $0          $0                $0                 $0
Total                  $80,120     $1,018,215        $566,665           $1,665,000

As the ATF grant is for construction only funding, matching the SEQ Liveability contribution, there
are incentives to keep non-construction associated costs to a minimum.

At the time of drafting this report, additional costs arising from additional community engagement
and project scope changes for Stage 1 have not been reconciled and will require further
consideration at Council's Capital Works Executive. It is noted that proposed design changes have
been scoped as reasonable considerations. There may be an opportunity for the construction
components of this work to be part funded through the ATF grant. The project team will continue to
pursue this opportunity.

Recommendations E and F, if supported, will require further consideration as part of Councils
budgetary processes, as well as profiling for grant opportunities.


Risk & Opportunities
1. Base Case Risk

   Project timeline not meeting the funding deadline resulting in exposure of Council to the part/full
   project cost and needing to fund this from Council reserves

          a. Triggers:
               i.   Delay in commencement of construction works
               ii. Inability to deliver the approved scope due to delays during construction
               iii. Repairs to existing infrastructure prior to project commencement
Log in to download the original file

Report.pdf · 289 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.