PEREGIAN BEACH ACTIVE STREET - STAGE 1 PROGRESS UPDATE AND NEXT STEPS (Deferred from the General Committee Meeting dated 16 March 2026) · Report
ORDINARY MEETING 19 MARCH 2026
reduces reputation damage risk
by including community
requests and/or suggestions into
the project where possible.
Further recommendations Additional Community Project will need to be fully
outside of those drafted by staff Consultation and or significant funded by Council.
change to planning and design
Alternative design treatments
approach
will likely be more expensive
than the currently proposed
project.
Delays to delivery of walking
and cycling infrastructure.
Halt project Stop working on design and Council will need to fund works
cancel planned construction to date at an approximate value
works. of $150k.
May damage relationships with
funding bodies and potentially
limit further funding
opportunities.
Reputational damage for not
following through with Walking
and Cycling Strategy objectives
and negative impact on future
projects proposals across the
shire.
Loss of funding for "practical"
components of the projects such
as construction of shared
pathway and rectification of
stormwater infrastructure.
Delays to delivery of walking
and cycling infrastructure.
Human Rights
Human Rights Compatibility Statement
In developing this Report, the subject matter has been considered in accordance with the
requirements of the Queensland Human Rights Act 2019. It is considered that the subject matter
does not conflict with any human rights and supports a human rights approach to decision making
by Council. Council representatives will endeavour to act and make decisions under this report in a
manner that is compatible with human rights. This report should be read in conjunction with
Council’s Human Rights Policy.
Consultation
External Consultation - Community & Stakeholder
Targeted community engagement throughout the concept and detailed design stages, focusing on
residents of South Peregian as well as key community and stakeholder groups as detailed in the