Original source · versioned page text
1912-14708 SRA - SARA response with conditions
Attached to the e-mail MCU19/0143 & OPW19/0264 - SARA Response.
1912-14708 SRA
Attachment 1—Referral agency conditions
(Under section 56(1)(b)(i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application)
Condition
No. Conditions
timing
Material change of use
10.4.3.1.1 – Premises contaminated because of unexploded ordinance—The chief executive
administering the Planning Act 2016 nominates the Director-General of the Department of State
Development, Manufacturing, Infrastructure and Planning to be the enforcement authority for the
development to which this development approval relates for the administration and enforcement of any
matter relating to the following condition(s):
1. Provide written confirmation to the Department of State Development, Prior to the
Manufacturing, Infrastructure and Planning by an approved contractor on the commencement
Australian Government, Department of Defence, Unexploded Ordnance (UXO) of works
Panel that the subject site has been remediated and cleared of Unexploded
Ordnances.
The Unexploded Ordnance (UXO) Panel is found online at:
http://www.defence.gov.au/estatemanagement/support/dehp/WhoToEngage.asp
Department of State Development, Manufacturing, Infrastructure and Planning Page 4 of 6