SUPERSEDED Decision Notice - 010.2008.00000066.001 [As Published] · 142008.66
2008/66
3.25. Nomo grass ‘Nomo’.
4. All manholes, inspection pits and grates are to be raised to finished surface levels and kept
free of cover and be visible at all times to ensure prompt access in case of emergency.
5. The landscape construction is to be implemented in accordance with the amended landscape
plan, planting schedule and horticultural industry best practices.
6. All trees must be planted a minimum of 1 metre from all services.
7. All trees 45 litre and greater must be securely tied and staked to assist their growth during the
establishment period.
8. All native plant species located in group plantings shall not be subjected to any hedging
maintenance regimes.
9. The density of planting must achieve the set out requirements as detailed on the approved
landscape plan.
10. The applicant must ensure that all landscaping treatment does not unduly restrict/prevent
access to service meters within the site.
11. The development of the site shall be carried out in such a manner as to prevent dust and/or
sand nuisance to residents in the vicinity of the development.
12. The requirements of this development approval are to be effected, prior to the use of the
relevant premises. Council reserves the right to call upon the bond or guaranteed sum
applicable to the overall site to effect compliance with conditions.
13. This Preliminary Approval lapses if the development has not happened by 25 July 2010,
unless application to extend the currency is approved by Council.
Carparking, access, stormwater drainage, erosion & sediment control
14. The development shall be carried out in accordance with the approved plans listed below or as
modified herein.
15. Copies of the approved plans (incorporating any modifications required due to conditions
contained herein) duly signed by the consultant Registered Professional Engineer of
Queensland (RPEQ) shall be provided to Council’s Construction Technical Officer at the “pre
start” meeting.
16. The filling of the site and construction of the proposed building and fencing shall not create
additional ponding of stormwater on any adjoining property.
17. Roof and surface runoff connection to Council’s kerb and channel shall be as shown on Spice
Consulting’s Drawing No. 686-01, A. Kerb adaptors shall be used in the kerb.
18. A 1.5 metre wide concrete footpath shall be constructed across the full frontage of the
development. The alignment shall be determined on site with Council’s Construction Technical
Officer. The footpath shall have a slip resistant surface. The expansion joints in any
bikeway/footpath shall be “saw cut”, not trowel jointed.
19. The vehicular access driveway serving the development shall be constructed with a maximum
width of 4.5m.
20. The driveway and any associated fencing or vegetation shall comply with the minimum sight
line requirements as defined in AS2890.1, sec 3.2.4.
21. Council’s Construction Technical Officer (ph 0410 512 505) shall be given seven (7) days’
notice of intention to commence works to arrange a “pre start” meeting prior to the
commencement of works.
Page 3 of 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice - 010.2008.00000066.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 62 KB (small file)
- File type
No other editions are linked here.