                                                                   Officer:            Nadine Gorton
                                                                   Direct Telephone:   07 53296215
                                                                   Our Reference:      132008.176.05
                                                                   Your Reference:     22070

                 2 December 2022


                 Calile Malouf Investments Pty Ltd
                 C/- Project Urban
                 PO Box 6380
                 MAROOCHYDORE QLD 4558
                 [email protected]



                 Dear Sir/Madam
                                                   Information Request
                                                       Planning Act 2016

                 I refer to your application and advise that Council requires further information to satisfactorily
                 assess the proposal.
                 1.     APPLICATION DETAILS

                  Application No.               132008.176.05 132008.176

                  Street Address:               3 Serenity Cl Noosa Heads Qld 45677 Serenity Cl Noosa
                                                Heads Qld 4567

                  Real Property Description:    Lot 10 SP 335472

                  Planning Scheme:              Noosa Plan 2020 (25 September 2020)

                 2.     INFORMATION REQUIRED

                 The information requested is set out below:
                 Tourist Accommodation zone
                 Issue – Plans
                 Further information is required to be submitted to demonstrate the external views of the
                 proposed resort and impacts on the surrounding streetscape and landform as the plans
                 provided lack detail and clarity. Further information is sought in relation to the existing and
                 finished ground levels, retaining walls, internal walls/arbours and fencing when viewed from
                 the street and surrounds.
                 Further plans are also required as to the rectangular structure in the norther eastern corner of
                 the site adjacent to Villa 15.
                 Information Required
                 1.     Provide further elevations and renderings for all views that clearly demonstrate:
                        1.1. Elevations from the existing and finished levels (the elevations provided appear to
                             have been taken from the street.
                        1.2. the existing and finished levels of the proposed development


                                               PO Box 141                   P. (07) 5329 6500          [email protected]
                                               TEWANTIN QLD 4565            F. (07) 5329 6501          www.noosa.qld.gov.au
                                                                                                                 Page 1 of 11
Document Set ID: 22193361
Version: 3, Version Date: 02/12/2022
Log in to download the original file

Information Request 132008 176 05.pdf · 1.2 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 10 pages

Page 2

                        1.3. proposed retaining walls on site including materials
                        1.4. proposed fencing and materials
                        1.5. basement openings and surrounding retaining structures and relationship to the
                             street
                        1.6. a section from the eastern edge of the development through the site.
                        1.7. provide plans of Sections G and H.
                 2.     Provide further plans that detail:
                        2.1. the materials of the wall behind the ‘quiet pool’ and how this is viewed from the
                             street
                        2.2. how the treatment pool area relates to the street level
                        2.3. a section from the western edge of the development through the treatment pools,
                             lawn, central retail area and units
                 3.     Provide further plans that detail a 6 metre setback to the retaining walls associated with
                        the ‘treatment pools’. The plans are to detail the retention of existing vegetation along
                        the frontage.
                 4.     Provide further plans or information about the rectangular structure in the north eastern
                        corner of the site


                 Issue - Height
                 AO9.1 of the Tourist Accommodation Zone Code details a building height of no more than 15
                 metres. The proposed service lift is detailed at 18.9 metre and is not supported. Further
                 information is required to review the proposed height of the development
                 Information Required
                 5.     Provide revised plans detailing the height of the proposed service lift compliant with the
                        15 metre height limit.
                 6.     Provide a further section through the proposed service lift area.
                 7.     Provide revised elevations and roof plans that clearly detail R.L.s for the top of all
                        buildings and plant on the site.
                 8.     Provide a survey plan of the site prepared by a registered surveyor. The plan is to
                        includes a survey of all frontages to the back of kerb of the opposite lots and include
                        existing vegetation


                 Issue – Site Cover
                 PO11 of the Tourist Accommodation Zone Code details a maximum site cover of 40% for the
                 site. The calculations have excluded the covered outdoor dining areas of the villas.
                 Information Required
                 9.     Provide amended calculations that include the covered outdoor dining areas of the villas
                        and demonstrate compliance with site cover.
                 10.    Provide further information with regard to the permanent cabana structures located
                        around the pool area.




                                                                                                         Page 2 of 11
Document Set ID: 22193361
Version: 3, Version Date: 02/12/2022

Page 3

                 Issue – Vegetation Removal within front Setbacks
                 Concerns are raised as to the location of the rapid infiltration swale located in the front
                 boundary setback of Serenity Close. The Landscape Concept Plan details that the swales are
                 located in the ecological area inside the boundary and will comprise low level, robust native
                 ground covers. The swale is over 7 metres in width and extends approximately 60 metres
                 across the frontage of the site. The swale does not allow for the provision of a landscaped
                 buffer to screen the development.
                 The location of these pits along the front boundary are not supported.
                 The proposal plans further detail the location of pools for Villas 1 to 15 within 1.5 metres of the
                 Serenity Close frontage. The pools are setback approximately 1.5 metres from the front
                 boundary with each unit having a private access to Serenity Close. The pools and pathway
                 result in a minimal landscape setback to Serenity Close and no opportunities for the retention
                 of vegetation. This presentation is not consistent with the character or amenity of the area and
                 is not supported.
                 Information Required
                 11.        Submit amended plans detailing:
                            11.1. Removal of the rapid infiltration swale from the front 6 metre setback to Serenity
                                  Close
                            11.2. Removal of the individual pathways from Villas 1 to 15 to Serenity Close
                            11.3. An increased vegetated landscape setback to Serenity Close. The plan is to detail
                                  the retention of existing vegetation along Serenity Close.
                            11.4. A dense landscape buffer to the north eastern corner of the site and Banksia
                                  Avenue including retention of existing vegetation


                 Issue – Design
                 The Tourist Accommodation Code details that development is designed to response to the
                 sub-tropical climate of Noosa, be of a scale compatible with the surrounding area and not
                 present an appearance of bulk. The Acceptable Outcomes detail requirements for small
                 separate buildings with no more than 6 units attached in one plane (AO14.6) as well as
                 buildings not to have unbroken elevation longer than 15 metre.
                 PO14 also specifically states:
                       f) has a form and architectural scale that does not dominate the streetscape or the
                          surrounding properties;
                       g) does not detract from the visual amenity of adjoining properties such as the impact on
                          views, access to sunlight or overlooking;
                       h) takes the form of small separate buildings, rather than large single bulky development;
                       i) sits within a landscaped setting; and
                       j) visually screens site utilities or integrates them with the design of the development.
                 Building scale and form is also referenced in the Noosa Heads Local Plan Code and the Visitor
                 Accommodation Code. AO7.1 to AO7.4 of the Noosa Heads Local Plan Code detail design
                 requirements relating to small separate buildings that do not dominate the street and respect
                 the scale of the surrounding vegetation. AO7.5 further details the provision of articulated roof
                 forms, a mix of lightweight materials, variation through articulation and texture and open
                 balconies or shaded patios with open transparent or semi open balustrades.




                                                                                                             Page 3 of 11
Document Set ID: 22193361
Version: 3, Version Date: 02/12/2022

Page 4

                 The proposed built form does not meet the Performance Outcome and provides a large bulky
                 development with limited opportunities for meaningful landscaping around and through the
                 site due to the extensive paved areas. The proposal plans do not meet the outcomes in relation
                 to the number of attached units and does not comprise small separate buildings. The buildings
                 uniformity, limited separation/ break between units, extensive flat planes and walls does not
                 respond to the sub-tropical climate of Noosa and is not supported.
                 Information Required
                 12.        Provide amended plans that provide smaller buildings separated by meaningful
                            landscaping (not lawns or pool areas).
                 13.        Provide more variation to the design of the units to remove the uniformity and repetition
                            of the development and meet the outcomes of the Codes.
                 14.        Provide amended plans that reference the sub-tropical climate of Noosa for the
                            development including articulated roof forms , lightweight materials, greater overhangs,
                            use of different building materials, softening of the edges of the building by removing the
                            boxy profiles..


                 Issue – Roof Form
                 PO 20 of the Tourist Accommodation Zone Code details requirements that must be addressed
                 where roof top terraces are proposed. PO 20 states:
                 Roof forms:

                       a)    contribute positively to the local skyline;
                       b)    complement the character of the locality and the topography of the site;
                       c)    avoid box profiles/parapets; and
                       d)    do not create opportunities for overlooking the private open space or internal spaces
                             of neighbourhood properties.
                 The proposed roof form does not meet the above Performance Outcomes as the boxy profile
                 proposed is not consistent with the character of the area, will not contribute positively to the
                 locality and is of a boxy profile. The roof form is not supported.
                 Information Required
                 15.        Provide amended plans that provide a more varied roof form that is consistent with the
                            character of the area, the subtropical climate and avoid box profiles.


                 Issue – Vegetation Removal
                 The arborists report has not been fully reviewed and a further request may be forthcoming
                 when it has been reviewed.
                 Information Required
                 16.        Further information is to be provided regarding the existing vegetation along Serenity
                            Close and Banksia Avenue and opportunities for retention.
                 17.        Concerns are raised as to whether the existing trees located near at the entrance to the
                            basement are able to be retained with the excavation proposed. Further detailed plans
                            are to be provided demonstrating the proposed levels and cut required for the driveway
                            and tree location.




                                                                                                              Page 4 of 11
Document Set ID: 22193361
Version: 3, Version Date: 02/12/2022

Page 5

                 Issue - Zoning
                 The southern portion of the site is included in the Environmental Management and
                 Conservation Zone and the proposal plan indicate earthworks, sheet piling and a rapid
                 infiltration swale within this zone ALTA Engineering Plan A676922PEW01. The assessment
                 table for the zone indicates that a Resort is an inconsistent use in the zone, and the proposed
                 works are not considered appropriate or consistent with the zone. The area is to be retained
                 for dense landscaping and screening.
                 The plan also indicated earthworks and sheet piling occurring within Councils reserve which
                 is not permitted.
                 Information Required
                 18.       Provide amended plans that remove the sheet piling and rapid infiltration swales from
                           the Environmental Management and Conservation zone.
                 19.       Remove any details of works within Councils reserve. All reports and plans are to be
                           amended to remove these works from the reserve.


                 Issue Transport - Ferry
                 The Sustainability Strategy lodged with the application indicates that the hotel will provide a
                 shuttle boat to ferry people to and from Hastings Street. No information has been provided
                 about the frequency of service or where the ferry will be moored noting that the jetty is a public
                 facility.
                 Information Required
                 20.       Provide further information regarding the ferry including:
                           20.1. Frequency of service
                           20.2. Estimates of patron/ passenger numbers
                           20.3. Where the ferry is to be moored and how it will be accessed
                           20.4. Arrangements in relation to access to destination jetties


                 Issue - Stormwater drainage
                 While not wanting to discourage innovation, the RIP system does appear to be a high-
                 maintenance solution and at high-risk of failure compared to conventional drainage. A lower
                 risk drainage solution which still achieves the infiltration targets could be achieved through
                 conventional drainage and provision of pipeless biofiltration systems.
                 Information Required
                 21.       Provide further information on the proposed rapid infiltration pits (RIPs) and justify the
                           suitability compared to a conventional drainage solution, and specifically address the
                           following:
                       •    The SWMP Appendix D spreadsheet calculations seem to use an impervious
                            catchment area for the external catchment of 4437m2, whereas the catchment plan
                            shows an area of ~1.1ha. Clarify this apparent discrepancy.
                       •    Provide current infiltration test data on the existing RIPs to demonstrate the infiltration
                            rates both in the current state of the devices and following the routine maintenance
                            required by the management plan
                       •    Update the maintenance plan for the RIPs to include a performance objective of ‘No
                            ponding of water within RIPs between rainfall events’ or similar




                                                                                                              Page 5 of 11
Document Set ID: 22193361
Version: 3, Version Date: 02/12/2022

Page 6

                       •    Explain what structures will be present over the 600mm dia emergency relief pipe
                            and how this pipe will be able to be accessed should maintenance or upgrade be
                            required in the future
                       •    Explain why a more conventional solution (eg conventional drainage and pipeless
                            bioretention) could not be adopted for the site and would not present a lower-risk and
                            lower-maintenance solution


                 Issue – Stormwater quality
                 Stormwater quality is not directly addressed in the SWMP - presumably on the basis that all
                 flows are infiltrated and hence ‘lost’. This does not recognise that groundwater is a receiving
                 environment and treatment is required prior to infiltration
                 Information Required
                 15. Provide an updated SWMP and preliminary engineering and layout plans which
                     demonstrate that stormwater quality objectives are achieved prior to discharge to
                     groundwater (i.e. prior to infiltration).


                 Issue – Grant/Banksia Roundabout Upgrade
                 Page 18 of TTM’s Traffic Engineering Report (22135916) dated 07 October 2022 details
                 design modifications of the existing Grant/Banksia roundabout and “Driveway Entry” into the
                 Resort. The submitted documentation does not contain sufficient information for Council to
                 assess the proposed Grant/Banksia roundabout upgrade and “Driveway Entry”.
                 Information Required
                 22.       Provide additional detail demonstrating the extent of the Grant/Banksia roundabout
                           upgrade and proposed ‘Driveway Entry’ into the Resort. The detail must be prepared by
                           a suitably qualified person (RPEQ – Registered Professional Engineer of Queensland)
                           and include, but not be limited to:
                           a. Demonstrate the extent of roadworks, including:
                                  i.   design alterations to the roadway, traffic islands and roundabout island;
                                  ii. signage; and
                                  iii. line-marking.
                           b. Demonstrate the extent of entrance works, including:
                                  i.   demonstrate the design of the proposed “Driveway Entry” complies with
                                       Noosa Council’s standard drawing RS-051;
                                  ii. provide a longitudinal section extending from the centreline of the road
                                      formation about the Grant/Banksia roundabout to the “Driveway/Setdown”
                                      area;
                                  iii. demonstrate B99 vehicle will not scrape or bottom out while entering and
                                       exiting the proposed “Driveway Entry”;
                                  iv. demonstrate additional stormwater runoff generated by the downward slope
                                      of the proposed “Driveway Entry” will create a worsening of drainage
                                      conditions within the road reserve and road network; and
                                  v. demonstrate the required vegetation clearing.




                                                                                                            Page 6 of 11
Document Set ID: 22193361
Version: 3, Version Date: 02/12/2022

Page 7

                 Issue – Serenity Close Cul-de-sac Upgrades
                 Page 18 of TTM’s Traffic Engineering Report (22135916) dated 07 October 2022 details
                 design modifications of the existing cul-de-sac at the end of Serenity Close. The submitted
                 documentation does not contain sufficient information for Council to assess the proposed
                 Serenity Close cul-de-sac upgrade.
                 Information Required
                 23.    Provide additional detail demonstrating the extent of the Serenity Close cul-de-sac
                        upgrade. The detail must be prepared by a suitably qualified person (RPEQ – Registered
                        Professional Engineer of Queensland) and include, but not be limited to:
                        a. Demonstrate the extent of cul-de-sac roadworks, including:
                                  i.   demonstrate the proposed services entrance generally complies with Noosa
                                       Council’s standard drawing RS-051;
                                  ii. provide a longitudinal section extending from the centreline of the road
                                      formation about the Serenity Close cul-de-sac roundabout to the “Loading”
                                      area;
                                  iii. Demonstrate the expected service vehicles (SRV, MRV, LRV BCC and
                                       VOLVO B12 BLE) will not scrape or bottom out while entering, manoeuvring
                                       on site and exiting the proposed servicing/loading entrance.
                        b. Demonstrate how the additional stormwater runoff generated by the downslope
                           slope of the entrance will be controlled, treated and released.
                        c. Provide comment on the amount of additional catchment volume during up to, and
                           including, a 1% AEP event and if the downstream drainage system has sufficient
                           capacity to handle this increase.


                 Issue – Practicality and Functionality of the Coach
                 Engineering is concerned the use of the coach is impracticable. The functionality of the coach
                 manoeuvring is impracticable and is likely to adversely affect the existing road network
                 conditions.
                 Information Required
                 24.    Provide additional detail demonstrating the coach is capable of manoeuvring through
                        the existing road network without adversely affecting the existing traffic conditions. The
                        detail must be prepared by a suitably qualified person (RPEQ – Registered Professional
                        Engineer of Queensland) and follow the below route:
                        a. Enter the Grant Street/Noosa Drive/Sunshine Beach Road roundabout via the west
                           (Noosa Drive) and south (Sunshine Beach Road);
                        b. Grant Street via the Grant Street/Noosa Drive/Sunshine Beach Road roundabout;
                        c. Banksia Avenue (north) via the Grant Street/Banksia Avenue roundabout;
                        d. Serenity Close via Banksia Avenue;
                        e. Proposed Coach parking bay via Serenity Close;
                        f.   Manoeuvre using the cul-de-sac;
                        g. Banksia Avenue via Serenity Close;
                        h. Grant Street via the Grant Street/Banksia Avenue roundabout;
                        i.   Noosa Drive (west) via the Grant Street/Noosa Drive/Sunshine Beach Road
                             roundabout; and




                                                                                                         Page 7 of 11
Document Set ID: 22193361
Version: 3, Version Date: 02/12/2022

Page 8

                        j.   Sunshine Beach Road the Grant Street/Noosa Drive/Sunshine Beach Road
                             roundabout.
                 25.    Provide additional detail demonstrating how the manoeuvrability of the coach will affect
                        and be affected by the existing on-street parking arrangements along Serenity Close.
                        The additional detail must consider all possible turning paths of the coach and be
                        prepared by a suitably qualified person (RPEQ – Registered Professional Engineer of
                        Queensland).
                 26.    Provide additional detail and comments demonstrating how the VOLVO B12 BLE will
                        enter the site in a forward gear and manoeuvre using the cul-de-sac without any
                        component of the coach (including 0.3m clearance) mounting the kerb, crossing the
                        coach bay line-marking or entering any private driveways. The detail and comments
                        must be prepared by a suitably qualified person (RPEQ – Registered Professional
                        Engineer of Queensland).
                 27.    Provide comment detailing the viability of alternate methods of transporting guests of
                        the Resort (i.e. utilising the existing Noosa Junction Bus Interchange to transport guests
                        to the Resort using a small vehicle that will have a lesser impact on the road network
                        compared to a coach).


                 Issue – Internal Carparks
                 Engineering is concerned that a number of the proposed internal carparks are not functional.
                 Information Required
                 28.    Provide additional detail demonstrating the highlighted carparks (extracted by Richards
                        & Spence’ SD-A-01-02-G_LEVEL 02-RevS) are functional. The detail must be prepared
                        by a suitably qualified person (RPEQ – Registered Professional Engineer of
                        Queensland) and include, but not be limited to:
                        a. Turning Path Plans indicating a B99 vehicle can enter and exit the highlighted
                           carparks without any component of the vehicle (excluding 0.3m clearance) colliding
                           with another vehicle or parking infrastructure. The plans must demonstrate that the
                           adjacent (or opposite, where applicable) carpark is occupied.




                                                                                                         Page 8 of 11
Document Set ID: 22193361
Version: 3, Version Date: 02/12/2022

Page 9

                 Issue - Parking
                 The traffic report has not been fully reviewed by Council Traffic Consultant and a further
                 request may be forthcoming when it has been reviewed.


                 Issue – Extent of Earthworks
                 Alta’s Preliminary Earthworks Layout plan (A676-22-PEW01) dated 5 October 2022 indicates
                 the proposed excavation earthworks and does not detail the earthworks required for the
                 proposed development as a whole.
                 Alta’s Preliminary Earthworks Layout plan (A676-22-PEW01) dated 5 October 2022 makes
                 reference to the manufacturer’s design & certification. Engineering has not received any
                 documentation pertaining the design, standard detail, anchoring notes and recommendations
                 or certification of the sheet piling.
                 Engineering has identified that the extent of sheet piling and installation of temporary battering
                 extends beyond the property boundary at the north- and south- eastern corners of the subject
                 site.
                 Information Required
                 29.    Provide an Earthworks Plan demonstrating the extent of the proposed earthworks
                        required to carry out the proposed development. The additional plan must be prepared
                        by a suitably qualified person (RPEQ – Registered Professional Engineer of
                        Queensland) and include, but not be limited to:
                        a. the extent and volume of cut and fill; and
                        b. Additional detail indicating whether the excess earth will be transported off-site or
                           temporarily stored on-site. If the excess earth is being transported off-site, provide a
                           construction management plan including truck routes.
                             Note that temporary on-site storage piles must be suitably treated to ensure short-term
                             stabilisation
                 30.    Provide additional plans demonstrating the extent of the sheet piling. The plan must be
                        prepared by a suitably qualified person (RPEQ – Registered Professional Engineer of
                        Queensland) and include, but not be limited to:
                        a. Standard detail of the sheet piling, including any required anchoring methods and
                           locations (note that all anchoring must be contained within the subject site);
                        b. Construction methodology of the proposed sheet piling;
                        c. Depth of the sheet piling; and
                        d. Comment on how the sheet piling will affect the proposed stormwater culvert and
                           other existing site features (trees, services, etc.).
                 31.    Provide comment on the sheet piling extending beyond the north- and south- eastern
                        boundary. The comment must be prepared by a suitably qualified person (RPEQ –
                        Registered Professional Engineer of Queensland) and consider:
                        a. the extent of development (including anchoring) must be kept within the property
                           boundary; and
                        b. the safety of pedestrians.




                                                                                                           Page 9 of 11
Document Set ID: 22193361
Version: 3, Version Date: 02/12/2022

Page 10

                 Issue – Acid Sulfate Soils Management
                 Council have identified that the proposed development is encumbered by Council’s Acid
                 Sulfate Soils hazard overlay. The submitted documentation does not include an Acid Sulfate
                 Management Plan or make reference to a Dewatering Plan.
                 Information Required
                 32.    Demonstrates through a geotechnical report, if the proposed development triggers
                        assessment against the Acid Sulfate Soils Overlay Code of The Noosa Plan 2020. If
                        assessment is required, provide a site specific Acid Sulfate Soils Management Plan. The
                        Acid Sulfate Soils Management Plan must be prepared by a suitably qualified person
                        (RPEQ – Registered Professional Engineer of Queensland).
                 33.    Demonstrate through a geotechnical report, that the proposed development will not
                        encounter water during excavations. If the proposed development is likely to encounter
                        water during excavation, provide a Dewatering Plan demonstrating how Acid Sulfate
                        affected water encountered during excavation will be treated and disposed of. The
                        Dewater Plan must be prepared by a suitably qualified person (RPEQ – Registered
                        Professional Engineer of Queensland).


                 Issue – Erosion and Sediment Control
                 The proposed development will alter the existing drainage conditions of the site during
                 construction. Council is concerned how sediment leaving the site will be controlled and treated
                 and how erosion of the site and neighbouring properties will be managed.
                 Information Request
                 34.    Provide a Sediment and Erosion Control plan that demonstrates how the site will control
                        contaminates leaving the site without causing erosion damage to the site and
                        neighbouring properties. The plan must be prepared by a suitably qualified person
                        (RPEQ – Registered Professional Engineer of Queensland) and include, but not be
                        limited to:
                        a. a Maintenance Plan that includes:
                                  i.   maintenance timeframes
                                  ii. quantitative or qualitative method of assessing the functionality of each
                                      measure
                                  iii. review of overall measures
                        b. Demonstrate how water collected on site will be treated before being leaving the site
                           (bio-basin, etc.).


                 3.     DUE DATE FOR RESPONSE TO INFORMATION REQUEST

                 The due date for providing the requested information is 2 March 2022. Email your response
                 to [email protected]. Please advise Council of your response to this information request
                 in accordance with section 13 of the Development Assessment Rules.
                 If you do not provide a response before the due date, it will be taken as if you have decided
                 not to respond to the information request and Council will continue with the assessment of
                 your application.
                 4.     OTHER DETAILS

                 You can follow the progress of this application online at www.noosa.qld.gov.au. The “Online
                 Services” page can be accessed via "Quick Links" on the left hand side of the screen.



                                                                                                      Page 10 of 11
Document Set ID: 22193361
Version: 3, Version Date: 02/12/2022

Page 11

                 Should you have any further queries in relation to the above, please do not hesitate to contact
                 me on the number above.
                 Yours faithfully,




                 Nadine Gorton
                 Development Planner




                                                                                                      Page 11 of 11
Document Set ID: 22193361
Version: 3, Version Date: 02/12/2022

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.