Att6 - Noise Impact Assessment
Christian Youth Council
Environmental Noise Level Impact Assessment for Proposed Extensions to CYC Youth Camp,
48 Kabi Road, Cootharaba Page 20 of 22
Project 001
dB
80
70
60
50
40
30
20
02:00:00 AM 06:00:00 AM 10:00:00 AM 02:00:00 PM 06:00:00 PM 10:00:00 PM
LAeq LAF1 LAF10 LAF90
Cursor: 06/07/2022 10:45:00 AM - 11:00:00 AM LAeq=43.1 dB LAF1=46.9 dB LAF10=39.5 dB LAF90=32.0 dB
Day 5, Sunday 10 July 2022
Project 001
dB
80
70
60
50
40
30
20
02:00:00 AM 06:00:00 AM 10:00:00 AM 02:00:00 PM 06:00:00 PM 10:00:00 PM
LAeq LAF1 LAF10 LAF90
Cursor: 06/07/2022 10:45:00 AM - 11:00:00 AM LAeq=43.1 dB LAF1=46.9 dB LAF10=39.5 dB LAF90=32.0 dB
Day 6, Monday 11 July 2022
David Moore & Associates Pty Ltd Our reference: R22072.docx/D3681/Rev.0/25.08.2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.