10. Vehicle access to the site must be from the existing vehicle crossover location. The
vehicle access driveway must be in accordance with AS 2890.2:2002.
11. Any gate located on the access driveway must be setback a minimum of 6 metres from
the property boundary.
Car Parking
12. All servicing of the development, including the delivery and collection of vehicles, must
be undertaken on site.
13. A total of 52 car parking spaces must be provided and marked on the site, exclusive of
spaces used for display sales. Carparking must be provided on-site generally in
accordance with the approved plans. The works must be undertaken in accordance with
an Operational Works approval and must include in particular:
(a) 18 staff parking spaces within the total, which are clearly marked for that purpose
(b) provision of vandal resistant public lighting with intensities to satisfy the
requirements of Australian Standard AS1158: Public Lighting Code
(c) 2 disabled parking spaces within the total.
14. All car parking areas and access driveways must be maintained exclusively for vehicle
parking and manoeuvring and kept in a tidy and safe condition at all times.
15. All vehicles must enter and exit the site in a forward gear.
Stormwater
16. All stormwater runoff from the carparking area must be directed to the on-site drainage
system and discharged without causing scour or damage to any adjoining property.
17. The construction of the service vehicle turnaround area at the rear of the site must not
cause additional ponding of stormwater on the adjoining property.
18. All Stormwater 360 StormFilter and Enviropod stormwater quality treatment devices
must be routinely checked, serviced and cleaned in accordance with the manufacturer’s
recommendations. Records of all maintenance activities undertaken must be kept and
made available to Council upon request. Where replacement cartridges or other
necessary components for the system become unavailable, an alternative system is
required to be retro-fit into the development to achieve an equivalent pollutant reduction
outcome.
19. Prior to commencement of use, the applicant must provide a copy of a signed supply
agreement for the replacement of the StormFilter Cartridges, between the Property
Owner and the stormwater filtration system supplier. The supply agreement must be for
the replacement of each StormFilter Cartridge at least ten (10) times.
Water Harvesting
20. Operating rainwater harvesting tanks must be provided for the development. The
rainwater harvesting tank must have a storage volume of 20,000 litres and be provided
in accordance with Operational Works approval and located as shown on Figure 6
WSUD Locality Plan, listed in this Decision Notice.
Page 3 of 8
Document Set ID: 19839426
Version: 1, Version Date: 05/12/2014 Print Date: 30 September 2020, 2:15 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Att B - Development Approval Package MCU13_0153.01.pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.7 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.