                                                            DERM Permit number: SPCC03617211


CONDITIONS
General
1.   All works are to be constructed in accordance with the approved drawings and the specifications as detailed
     on these drawings.
2.   If acid sulphate soils are found to be present through testing of areas subject to excavation in accordance
     with the requirements of State Planning Policy 2/02, then the works must be managed to prevent acid
     sulphate soil development as outlined in the current version of the Queensland Acid Sulphate Soils
     Technical Manual Soil Management Guidelines.
3.   The disturbance to the bed and banks of the waterway is to be kept to a minimum.
4.   If as a result of any works, any bank is displaced the permit holder shall restore the bank to its original
     condition and take such other action as is necessary to ensure the stability of the bank to the satisfaction of
     the chief executive.


Construction
5.   All construction works on the jetty are to occur during times which would minimise sediment and
     contaminant dispersal.
6.   All excavated material shall be transported to an appropriate location outside of the Coastal Management
     District.
7.   Any material or any debris that falls or is deposited outside of the alignment of the works shown on the
     approved plans must be removed within 48 hours following placement of the material.
8.   All temporary works associated with the construction of the works are to be removed from the site at the
     completion of the works.
9.   All wastes shall be collected and disposed of at an appropriate lawful facility.


Water Quality
10. Construction of the works are to be carried out only by means of suitable plant and equipment and
    measures are to be taken to limit turbidity in tidal waters as a result of the construction.
11. All reasonable and practicable measures must be taken to prevent pollution of the waterway as a result of
    silt run-off, oil and grease spills from machinery, concrete truck washout and alike. Wastewater from
    cleaning equipment must not be discharged directly or in-directly to any watercourses.
12. If there are any signs of sediment loss, a filter fence or other erosion device to contain sediment
    contaminated water and prevent contamination of tidal waters, is to be installed and maintained until
    completion of the works.


Stormwater
13. Stormwater drainage systems are to be constructed to include quality improvement devices (sediment
    removal, gross pollutant traps) to ensure that stormwater can be effectively managed and discharged
    without causing adverse impact on the wetlands adjoining the subject land.


Demolition
14. All demolition materials that are to be removed shall be transported to an appropriate location outside of the
    Coastal Management District or other approved location.



Page 3 of 7 ' 091217                                                Department of Environment and Resource Management

Used in these records

About this file

File size
3.6 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Concurrence Agency Response 222 Gympie Terrace Noosaville.pdf · 3.6 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.