RATIONAL METHOD SUMMARY CALCULATIONS - EXISTING
CASE
Cachment ID Existing Compiled By: MR
Catchment Area, A (ha) 0.077 Checked By: LO
Date: 2024/11/01.
Project Name: 51 Elanda Street, Sunshine Beach
Project No: SSC-2401
Time of Concentration, t (min) 5.000
Impervious Fraction, fi 0.450
Land and Soil Permeability Description (if fi < 0.2)
1 Hour 1:10 year rainfall intensity at locality, 1I10 75.200
10 year Discharge Coefficient, C10 0.800
Rainfall Intensities, Iy (mm/hr): Coefficient of Discharge, Cy: Rational Method, Qy (l/s) : Difference from Post Dev
I63.20 125.00 C63.20 0.64 Q63.20 17.11 -1.71
I50 142.00 C50 0.64 Q50 19.44 -1.94
I20 193.00 C20 0.76 Q20 31.37 -3.14
I10 227.00 C10 0.80 Q10 38.84 -3.88
I5 259.00 C5 0.84 Q5 46.53 -4.65
I2 301.00 C2 0.92 Q2 59.23 -5.92
I1 333.00 C1 0.96 Q1 68.38 -6.84
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Stormwater Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 15.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.