Attachment E - Unitywater Advice Note

of 3

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                                Flow available          Residual Head
                                                                                              from Unitywater           in Water main
                                              Type of Use                                            Main               (meters)
                                                                                               (Litres/second)

                   Residential dwellings of less than 3 storey                                          15                        12

                   Commercial that is ancillary to residential use                                      15                        12

                   Multi Storey residential greater than 3 storeys                                      30                        12

                   Commercial and or Industrial                                                         30                        12


              Should an approval for connection be provided by Unitywater, the developer will need to
               apply to Unitywater for a Private Works Quote in relation to the cost for new metered water
               supply service connections and live connections to existing water/sewer infrastructure by
               Unitywater. A copy of the connection approval and associated approved plans detailing the
               new connections must accompany the private works quotation application. Please refer
               Unitywater’s website at http://www.unitywater.com/private-works. for further details.

              An existing 150mm diameter sewer main travers the lot 5 site. Unitywater’s preference is
               to relocate all sewers clear of any proposed building footprints. Any proposal to build over
               and/or adjacent to a Unitywater asset must be assessed under the Queensland
               Development Code (QDC) 1.4 – Building over or near relevant asset. (Refer
               www.hpw.qld.gov.au). This assessment could be performed through Private Building
               Certifier or Registered Professional Engineer of Queensland (RPEQ). Policy. Further
               information     on this process is available on                Unitywater’s website at
               http://www.unitywater.com/Building-and-development/renovating-or-extending

              All water supply and sewerage works must be designed and constructed in accordance with
               the South-East Queensland Water Supply and Sewerage Design and Construction Code,
               Unitywater’s Connections Administration Manual and any other matter Unitywater considers
               to be relevant to the connection or supply of its water services or wastewater services.

              Any change to Unitywater’s existing infrastructure as required by this proposal must be
               carried out at no cost to Unitywater.

              Payment of Levied Charges will be required in accordance with Unitywater’s Infrastructure
               Charges for water supply and sewerage.

                 If you have any queries about the advice, please contact                                                Unitywater             at
                 [email protected] or by phone on 1300 086 489.

                 Yours sincerely,
                 Development Services
                 Unitywater
                                                                                                                                  Page 3 of 3
Unitywater is a statutory authority that provides water and sewerage services for the                           Unitywater has certification to
                                                                                                                OH&S ISO 4801:2001 Reg No 4260
Moreton Bay, Sunshine Coast and Noosa Council areas.                                                            Environmental ISO 14001:2004 Reg No 4259
                                                                                                                Quality Systems ISO 9001:2008 Reg No 4258

                                                     Revision No: 2                Effective Date: 19/02/2015           Next Review Date: 19/02/2018
Log in to download the original file

Attachment E - Unitywater Advice Note.pdf · 568 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.