L03 To NSC - lodge DA
benefiting tenement for this proposed easement through Lot 2. The application incorrectly advised that
the proposed 4 metre wide easement would be registered for stormwater purposes in addition to
sewerage purposes given that the stormwater infrastructure within that easement will be privately owned
and maintained.
Item 2: Service Clearances
Applicant’s response to Item 2: The applicant engaged Bax Engineering as its third party certifier
for its dealings with Unity Water on this item. Please refer to the advice from Unity Water in Attachment
A.
Item 3: Capacity of Reticulated Sewerage Network
Applicant’s response to Item 3: The applicant engaged Bax Engineering as its third party certifier
for its dealings with Unity Water on this item. Please refer to the advice from Unity Water in Attachment
A.
The applicant has therefore responded to Council’s IR and requests that Council completes its assessment
of the above development application.
Please contact me if Council requires any further information and/or clarification in relation to this
development application.
Yours faithfully,
Greg Martoo
Principal
martoo consulting pty ltd
Encl (1)