Attached to the e-mail MCU17/0046 & OPW17/0160 - Response to Information Request.
5 July 2017
SCG Ref: 26361(L1)
By email: [email protected]
Lisa Pienaar, Development Planner – Noosa Council
C/- Martoo Consulting
Dear Lisa
Re: 38 Park Crescent, Sunshine Beach
MCU 17/0046 OPW17/0160
In response to the Information Request dated 6 June 2017 for the above we comment as follows: -
1. SCG Consulting Engineers (SCG) plans SCG 26361 have been updated to reflect the removal of the
north-western driveway and visitor carpark.
2. The reference to a Stormwater Management report on drawing SCG 26361-SW1 was made in error
and no report has been produced. Similar duplex developments that SCG has been the Civil Engineer
for have not required a report.
3. The drainage pits located within the road reserve have been removed. The grated drain along the front
property boundary has been increased in capacity to allow for the stormwater captured by these pits.
4. A schematic elevation of the charged stormwater line has been added to drawing SCG 26361-SW2.
The charged stormwater line has a slow leak pipe incorporated to allow drainage so it does not become
a ‘wet line’. In addition to this an inspection opening will be provided to allow back flushing should it
become blocked with debris.
5. The intent of the gravel scour protection is to diffuse the velocity of the stormwater discharge from the
grated drain. The gravel provides a harder, less erodible surface than the natural sand ground profile.
A section through the gravel scour protection beds has been provided on SCG 26361-SW2, further
explaining their function and proposed construction and maintenance.
6. The site coverage of the proposed development will capture and contain more stormwater that falls
over the site than, the pre-development conditions and therefore, reduce the total overland flow. All
stormwater captured on the hardstand within the road reserve will be contained in the site stormwater
disposal system.
7. In order to provide access to the south-western visitor carpark and maintain realistic driveway grades a
retaining wall will be required. The retaining wall will be of solid RC masonry construction with a design
life of 25 years plus. As the footpath is on the western side of Park Crescent there will be no adverse
impacts of pedestrian activity.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 1 page
Page 2
8. The proposed driveway sections A-A & B-B on SCG 26361-OW5 show the roll over high point to be the
same height or higher than the existing top of kerb on section A-A. Achieving a high point of 250mm
above the kerb invert is not possible without the driveway exceeding a maximum grade of 1:4 on section
B-B. A high point of 188mm above the kerb invert is achievable assuming the existing kerb height is
adequate, then the stormwater runoff should be contained within the road formation.
Yours faithfully
BEN HOPKINS
For and on behalf of
SCG CONSULTING ENGINEERS