Original source · versioned page text
Negotiated Decision OPW16/0235
DELEGATED REPORT PLANNING ASSESSMENT BRANCH REQUEST FOR NEGOTIATED DECISION NOTICE Application no: Author: Mark Lewis - Project Director: Mark Lewis - Coordinator Engineering SUMMARY: APPLICATION DETAILS Application Number: OPW16/0235 Applicant: Eenie Creek Holdings Pty Ltd Tte Representations Received Date: Original Approval Type: Development Permit for Operational Work - Stormwater, Landscaping & Civil works Number of Submissions for Original Application: Not applicable PROPERTY DETAILS Division: Property Address: 8 Eenie Creek Rd NOOSAVILLE QLD 4566 RP Description: Lot 9 SP 232770 Land Area: 1410.0000 Square Metres Existing Use of Land: Industrial STATUTORY DETAILS SEQRP Designation: Planning Scheme: The Noosa Plan (16 September 2013) Strategic Plan Designation: Planning Area / Locality: No planning area defined Planning Precinct / Zone: Assessment Type: Code BACKGROUND: A Preliminary Approval was issued on 6 January 2017. The approval was for “preliminary” only as the applicant had not submitted the performance bond described in the higher order approval. The bond was subsequently paid on 11 January 2017. The representations received by Council on 17 January 2017 requested Council issue a Development Permit. RECOMMENDATION AGREE to the representations submitted in relation to Application No. OPW16/0235, situated at 8 Eenie Creek Rd NOOSAVILLE QLD 4566 , and issue a Negotiated Decision Notice in accordance with the following:- A. Change the approval description/type to the following: Development Permit for Operational Works – Stormwater, Landscaping & Civil works B. Delete Condition 1 C. Include additional Conditions 2 - 29 D. Delete Advisory Note 1 E. Include additional Advisory Notes 2 – 12 APPROVED PLANS Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. Plan No. Rev. Plan/Document Name Date 1609-LP1 B Landscape Plan prepared by Mark Baldock Landscape Architect 24 November 2016 1609-LP2 B Landscape Plan prepared by Mark Baldock Landscape Architect 24 November 2016 10609-LP3 B Landscape Notes prepared by Mark Baldock Landscape Architect 24 November 2016 216130-S1 A Proposed Industrial Building 8 Eenie Creek Road, Noosaville prepared by JTC Consulting Engineers 17 October 2016 216130-S2 A Site Level Plan prepared by JTC Consulting Engineers 17 October 2016 216130-S5 A Stormwater Layout and Catchment Plan prepared by JTC Consulting Engineers 17 October 2016 216130-S6 A Concrete Joint Plan prepared by JTC Consulting Engineers 17 October 2016 216130-S7 A Concrete Details prepared by JTC Consulting Engineers 17 October 2016 216130-S11 B Carpark Layout Plan prepared by JTC Consulting Engineer 23 November 2016 PRIOR TO COMMENCEMENT OF WORKS Engineering Tree protection fencing must be installed under the supervision of the Project Arborist. (Refer to Retention of Existing Trees Conditions) All necessary approvals from external service providers (eg Unitywater) and external parties on which the development works are proposed have been obtained and a copy supplied to Council. Copies of the approved plans, duly signed by the consultant Registered Professional Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer Construction at the “pre start” meeting A condition report including photographs of the frontage of the site must be completed and submitted to council at the prestart meeting / prior to any works commencing. Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council at the prestart meeting. Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6245. The pre-start meeting must include the relevant parties for the following aspects of the works: Civil engineering works; Landscape works; A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following: appropriate traffic signage in accordance with the Manual of Uniform Traffic Control Devices (MUTCD) provision for safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased. Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring. Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works. DURING CONSTRUCTION Engineering The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers. All works must be constructed and work procedure undertaken in accordance with: The approved plans/documents and conditions detailed in this Decision Notice The relevant conditions of the higher order Material Change of Use approval viz. MCU16/0095 to which this approval relates All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site Pavement Design and Construction Pavement design for privately owned works must be undertaken in accordance with the relevant standards. Structural integrity of the driveway and car park areas will remain the responsibility of the property owner/developer and must be certified by an RPEQ. Works within Road Reserve/Reinstatement Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with. All frontage works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge/footpath profiles. Electrical conduits or other services proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council. Site Access and Driveways Any existing unnecessary or redundant property accesses must be removed, and the kerb, footpath and verge area reinstated to match the existing footpath and/or verge treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established. The following must be complied with during the construction of the required crossover/driveway: The driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete. The driveway must be constructed so as not to concentrate stormwater runoff onto neighbouring properties Underground service conduits for water supply, electricity and any other services must be provided as part of the access driveway Where there is an existing pedestrian path, a matching crossfall must be provided for the driveway on the alignment of the path, for the full width of the path The property access must be located a minimum of 1m clear of existing power poles, streetlights or other signage. The developer is responsible for any necessary relocation of existing services to provide this clearance and must contact the relevant service authorities and comply with their requirements in relation to these works. Earthworks and Retaining Walls All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines on Earthworks for Commercial and Residential Development, with geotechnical testing undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and uniformity of fill shall be provided by a RPEQ and submitted to Council prior to Council signing the Plan of Survey. Stormwater Drainage Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets. Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (eg by blocking or interfering with natural overland flows). Construction of all internal stormwater drainage works must comply with the relevant section/s of Australian Standard AS/NZS 3500.3. Environment Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination. Erosion and sediment control measures must be installed and maintained to minimise erosion on the site and to minimise the export of sediment and associated pollutants from the site. The erosion and sediment control measures must be designed, installed and maintained in accordance with current best practice standards (refer to advisory notes). Prior to the final inspection of the site all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term (refer to advisory notes). For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination. Limit soil exposure on the site to a distance of no more than 2m beyond the extent of earthworks shown on the approved plans except where the exposed soil is effectively stabilised without delay and prior to rainfall occurring. Damage to Services and Assets Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times: where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or where otherwise, upon completion of the works associated with the development. Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval. FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY Certification Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit. ADVISORY NOTES General Advisory Notes Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works. A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design. Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent. Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time. Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Sustainable Planning Act 2009 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees. Prestart, On and Off Maintenance Inspections Request Contact Council on 5329 6245 to arrange a prestart or an inspection giving a minimum of 5 business days notice of preferred inspection time. If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time. A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise Environmental Advisory Notes The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm. Erosion and Sediment Control Accepted best practice standards include: the Sunshine Coast Regional Council Manual for Erosion and Sediment Control V1.2 or other superseding document subsequently adopted by Council; Best Practice Erosion and Sediment Control, International Erosion Control Association (2008) Landscaping Qualified Person, for the purpose of: Managing Fauna protection is considered to be a certified Fauna Spotter Catcher Public amenity trees are defined as any tree located within public streets, parks or areas that will become publically owned as a result of this development. Aboriginal Cultural Heritage Act 2003 There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003. The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage.” It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage. You should contact the Cultural Heritage Co-ordination Unit on 07 3239 3647 to discuss any obligations under the ACH Act. REPORT COVER SHEET PLANNING ASSESSMENT BRANCH Application no: OPW16/0235 Author: Mark Lewis manager: Mark Lewis TO BE COMPLETED BY MANAGER / REPORT AUTHOR: Is the application required to be decided by the Iconic Panel?: Yes / No Is referral required to the Councillor Delegated Sign Off Mailbox?: Yes / No Has a site inspection been undertaken?: Yes / No Has Infrastructure Policy Branch been notified and a request for an Infrastructure Contributions calculation been made?: Yes / No Material to give to the Project Director □ A copy of any previous edited version of the report □ Plans and documents recommended to become Approved Plans and Documents □ Location plan / aerial photographs at appropriate scales □ Copy of all specialist advice and/or memos (or alternatively tagged in the file) □ Site photos (where obtained) □ Copy of all referral agency responses (or alternatively summarised in the body of the report) □ Copies of all adjoining approvals and past approvals for the site as may be relevant OFFICER MANAGER Signature: Signature: Position: Position: Coordinator Engineering Date: Date: TO BE COMPLETED BY PROJECT DIRECTOR: (Note: to be signed after the Councillor Delegated Sign Off referral process is completed (where applicable)) I exercise delegation in accordance with the delegations adopted by Council on <: Signature: Date: MANAGE [word/footer1.xml] Page 2 of 9 [Attachment: image1.png (image text)] a mm NOOSA COUNCIL
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original