Performance outcomes Acceptable outcomes Response Comment
mitigate adverse impacts to people and permanent
structures from coastal erosion at the location.
AND
AO6.4 Development that is temporary, readily relocatable The rising main is located within an existing easement for
or able to be abandoned, or essential community service sewage infrastructure and the design minimises the footprint
infrastructure: of the development.
(1) locates built structures landward of an applicable
coastal building line, or
(2) where there is no coastal building line, locates
habitable built structures landward of the alignment of
adjacent habitable buildings, or
(3) locates lifesaver towers or beach access
infrastructure to minimise its impacts on physical
coastal processes, or
(4) where it is demonstrated that (1) or (2) is not
reasonable and (3) does not apply:
(a) locates built structures as far landward as
practicable
(b) uses layout design to minimise the footprint of
the development that remains within the erosion
prone area.
AND
AO6.5 Redevelopment of existing built structures not N/A N/A
referred to in AO6.4, and excluding marine development:
(1) relocates built structures outside that part of the
erosion prone area that is within the coastal
management district, or
(2) relocates built structures as far landward as
practicable, and landward of an applicable coastal
building line, or
(3) where there is no coastal building line:
(a) relocates built structures landward of the
alignment of adjacent habitable buildings, or
(b) uses layout design to minimise the footprint of
the development that remains within the erosion
prone area, or
(c) provides sufficient space seaward of the
development within the premises to allow for the
construction of erosion control structures.
State development assessment provisions Module 10 — Coastal protection 10.1 Tidal works, or development in the coastal management district state code
6 July 2015 V1.6 Page 6 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
sdap-response-template-v1-6-10-1.pdfRelated documentApplication case desk ↗
About this file
- File size
- 271 KB (small file)
- File type
No other editions are linked here.