RESPONSE TO FURTHER ADVICE -Geotechnical Report · MCU25/0054

of 29

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                                                                      PTG/02023 – 0001 – Rev1



Table 3: Texture Based Action Criteria for ASS.
                Soil Texture                          1 – 1000 t disturbed                 > 1000 t disturbed

                                              Equivalent Sulfur      Equivalent                          Equivalent
                                                                                  Equivalent Sulfur
 Texture Category        Texture Range                                Acidity                             Acidity
                                                   (%S)                                (%S)
                                                                     (mol H+/t)                          (mol H+/t)

                         Sands to loamy
       Coarse                                       0.03                 18
                         sand and peats
                         Clayey sands to
      Medium                                        0.06                 36
                            light clays                                                 0.03                    18
                        Light, medium to
        Fine            heavy clays and             0.10                 62
                           silty clays

As sand-based soils were encountered in the boreholes and the samples tested, the applicable action criterion is
18 mol H+/t, irrespective of the quantity of soil to be disturbed.

The final area and volume of soil disturbance (cut and/or fill) below RL 5 m AHD must be assessed to determine if
further borehole drilling, sampling and testing is required.



10 LIMITATIONS
PTG Consulting has prepared this report (or services) for this project in accordance with PTG's proposal and
acceptance received from the Client. These limitations apply whether the report was created under PTG’s own terms
and conditions or otherwise.

This report is provided for the exclusive use of the SCG Consulting Engineers for the Geotechnical scope of works at
20 William Street, Noosaville. The report should not be used by or relied upon for other projects or purposes on the
same or other site or by a third party. Any party so relying upon this report beyond its exclusive use and purpose as
stated above, and without the express written consent of PTG, does so entirely at its own risk and without recourse
to PTG for any loss or damage. In preparing this report, PTG has necessarily relied upon information provided by the
client and/or their agents.

PTG's advice is based on information gained from limited subsurface excavations and sampling supplemented by
knowledge of local geology and experience. The accuracy of the advice provided by PTG in this report may be affected
by undetected variations in ground conditions across the site between and beyond the sampling and/or testing
locations. For this reason, our reports include an interpretation of conditions between the test points. There are
unknowns or variations in ground conditions between test locations that cannot be inferred or predicted. Such
variations may occur after PTG's field testing has been completed. The precision and reliability of interpretive
assessment between discrete points is dependent on the uniformity of the subsurface strata, as well as the frequency,
detail, and method of sampling or testing.

Geotechnical information represents an opinion and is based extensively on judgment of both data and interpretive
assessments or observation. This report and its associated documentation are provided explicitly based on PTG’s
opinion of the site at the time of inspection, and cannot be extended beyond this. Any recommendations or design
suggestions will need to be verified on site during project implementation or construction. Inspection and verification
on site may be conducted by a suitably qualified geotechnical consultant or engineer, and where subsurface conditions
or interpretations differ from those provided in this document or otherwise anticipated, PTG must be notified and be
provided with an opportunity to review the recommendations

The report has been prepared by qualified personnel, is based on the information obtained from field and laboratory
testing, and has been undertaken to current engineering standards of interpretation and analysis. The information and
interpretation may not be relevant if the development proposal is changed. If this happens then PTG will be pleased
to review the report and the sufficiency of the investigation work.

Every care is taken with the report as it relates to interpretation of subsurface conditions, and the discussion and
recommendations or suggestions relating to the geotechnical aspects of the scope of works. However, PTG cannot
always anticipate or assume responsibility for:
» Unexpected variations in ground conditions;
» Changes in policy or interpretations of policy by statutory authorities; or
                                                                                                                      11

Used in these records

About this file

File size
4.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

RESPONSE TO FURTHER ADVICE -Geotechnical Report.pdf · 4.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.