GENERAL COMMITTEE MEETING AGENDA 17 SEPTEMBER 2018
different calculations be undertaken for issuing a charge and 3 different calculations to
determine the actual indexation to apply when time comes for payment (i.e. using
variations in: CPI, current permissible maximum charge and/or 3-yearly PPI average). This
creates an unnecessarily complex process of calculation.
It is proposed to simplify Council’s “automatic increase provision” to one single indexation
method that will apply uniformly on the issue and subsequent payment of the charge that
will satisfy the current legislation i.e.
“annual indexation per Financial Year using variations applicable to the “maximum amount”
possible to be issued under the Planning Regulation 2017 as amended in accordance with
the legislation, from the stipulated base date to the time of issue and payment.”
The implication of Section 302 (Transitional provision) of the current Planning Act 2016 is
unclear in relation to payment of previously issued adopted infrastructure charges. It is
therefore proposed to apply the above indexation methodology to all remaining
infrastructure charges issued after 1 July 2011 under all previous “adopted” Council
charges resolutions to ensure consistency and limit potential legal risks.
However, CPI indexation will need to continue for all infrastructure contributions and/or
infrastructure charge notices remaining to be paid that were issued prior to 1 July 2011
under the former Planning Scheme Policies (PSP’s) contained as a condition of a
development permit and/or under the former Coastal Major Road Network Infrastructure
Charges Plan (CMRNICP). This will ensure these contributions/charges comply with their
specific legislative requirements under which they were issued. Similarly, infrastructure
charges and/or contributions under delayed staged payment or other infrastructure
agreements need to comply with the written legal agreements entered into at the time.
iv. Section 120 (1) of the current Planning Act 2016 stipulates, “A levied charge may be only
for extra demand placed on trunk infrastructure that the development will generate.”
Under Council’s LGIP that took effect on 8 June 2018 replacing the former PIP, the
stormwater network now only provides “trunk” infrastructure within the Priority Infrastructure
Area (PIA) urban service catchments. Therefore, Council’s charges resolution should
reflect that the stormwater component of the charge will only apply to development located
inside the PIA.
Since 8 June 2018, only five infrastructure charges notices have been issued on
development approvals located outside the PIA. Accordingly, these notices should be
reviewed and reissued with “amended” infrastructure charges notices removing the
stormwater component of the charge if applicable.
v. A number of recent court judgements have provided some clarity to a number of unclear
legislative provisions. Amendments to the current charges resolution are included to help
clarify some issues raised in recent court judgements.
vi. Table 10.3 Schedule of adopted charges has been simplified to show Unitywater’s and
Council’s charge rates according to the existing breakup agreement relating to the current
“prescribed amounts” under the Planning Regulation 2017 for the 2018-2019 financial year.
Any reductions for specific uses to Council’s charge rates as decided by Council, are then
detailed where applicable.
In accordance with discussions held during the Council workshop on 6 September 2018,
Council’s reduced charge rates have been maintained from the current resolution at the
CPI June 2018 indexed rates as the new 2018-2019 base rates for the following uses:
Multiple housing Types 2, 4 and 5 for 1 bedroom units;
Secondary dwelling to a detached house;
Multiple housing Type 3 Retirement and special needs; and
Entertainment and dining business Type 2 Recreation, amusement and fitness.
The amended Charges Resolution is provided as Attachment 1.
Page 6 of 48
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.