(b) have no “broad expanses of a single colour”;
(c) ensure walls are “broken up by varying tones or design elements.”
Despite the requirement to be generally consistent with the approved plans, the three dot point create uncertainty
as to whether the colour scheme on the approved plans would satisfy the condition.
We request that Council delete the dot point above elements from the condition. Alternatively wording in the
condition needs to be revised to make clear the that the colour scheme on the approved plans do satisfy the
condition requirements.
2.4 Condition 15d – street trees
The development has a road frontage of 50 metres to Gateway Drive. The current wording of the condition would
require the development to provide seven (7) street trees to that street frontage.
The condition does not account for practical road frontage being limited by the width of the entry and exit
crossovers. The crossovers are a total of approximately 33 metres of the frontage. This leaves 17 metres of actual
frontage to accommodate street trees, making it not possible to accommodate 7 trees. Figure 9 illustrates the
extent of the frontage and the limited opportunity for additional street trees.
Figure 9 – Street Frontage Planting
In discussing with the landscape architect, it has been advised that additional two (2) street trees can be
accommodated within the road reserve. Accordingly, we request that the wording of the condition be amended to
require a total of 3 street trees within the road reserve opposed to the current provision of 1 per 8 metres of road
frontage.
2.5 Condition 20 – security bond
This condition requires a $20,000 security (cash bond or bank guarantee) to be provided to Council prior to the
issue of a development permit for operational works, to secure performance of the conditions of the approval.
This appears to assume that Bunnings will not comply with the approval, which is contrary to a proper legal
approach. Further, it is unclear how long the security needs to be maintained given that some conditions will need
to be maintained over the life of the development (e.g. condition 16).
Mechanisms exist under the Planning Act 2016 to address non-compliance with conditions.
We request this condition be deleted.
2.6 Conditions 21, 39 and 40 - ASS
Conditions 21, 39 and 40 relate to carrying out an acid sulfate soils investigation and potential preparation of an
Acid Sulfate Soils Management Plan if required. There is some overlap in the requirements of condition 21 as
compared with conditions 39 and 40.
RPS AAP Consulting Pty Ltd. Registered in Australia No. 97 117 883 173
rpsgroup.com Page 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
MCU22-0051_Change Representations_v1.4_041223.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.4 MB (small file)
- File type
No other editions are linked here.