Decision Notice - Approved by Delegation of Authority OPW23 0139 · OPW23/0139
a. have approval of the bond calculations and amount from Council prior to lodgement
b. be lodged with Council and accompanied by the Bond Administration Fee/s.
c. be requested for release by writing to Council, when relevant approval requirements
have been met.
PRIOR TO COMMENCEMENT OF WORKS
Landscaping Works
5. Landscape works must be supervised, undertaken and certified by qualified persons*. All
works must be completed in accordance with this Decision Notice and must include in
particular:
a. the works generally shown on the Approved Plans except where varied by the
conditions of this approval. The landscape plans must be resubmitted prior to a prestart
meeting.
6. Prior to requesting a prestart meeting provide:
a. Receipt of amended plans approval.
Engineering
7. All necessary approvals from external service providers (e.g., Unitywater) and external
parties on which the development works are proposed have been obtained and a copy
supplied to Council.
8. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting / prior to any works commencing.
9. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
10. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Erosion and sediment control works; and
c. Other relevant parties
11. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic management during all phases of construction;
b. Adequate parking arrangements for works and deliveries;
c. appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD); and
d. provision for safe vehicle and pedestrian access across the frontage of the site both
during daily construction and after daily construction has ceased.
12. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
13. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
Page 3 of 9
Document Set ID: 23157052
Version: 3, Version Date: 07/08/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Approved by Delegation of Authority OPW23 0139.pdfRelated documentApplication case desk ↗
About this file
- File size
- 167 KB (small file)
- File type
No other editions are linked here.