55. All stormwater quality treatment devices must be maintained in accordance with the
Water by Design (2009) Maintaining Vegetated Stormwater Assets (Version 1). The
approved Operational Works drawings for the stormwater quality treatment system and
detailed life cycle costing of the system must be attached as an addendum to this
document. Records of all maintenance activities undertaken must be kept and made
available to Council upon request.
56. Operating roof water harvesting tanks must be provided for the development. The tanks
must be provided in accordance with an Operational Works approval and must include
in particular:
a. a total tank capacity of 135,000 litres
b. a catchment of not less than 2,800m2 of the building roof area
c. re-use of harvested stormwater for non-potable outdoor uses including irrigation
of landscaped areas and swimming pool top-up.
57. Certification must be submitted to Council from a qualified person which certifies that
the stormwater harvesting tanks and associated reticulation has been installed in
accordance with the requirements of this Decision Notice.
Acid Sulfate Soils
58. An Acid Sulfate Soil Management Plan must be prepared and submitted with the
Operational Works application for the site. The acid sulfate management plan must
include testing, monitoring and treatment requirements for the works.
Services
59. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits and
pipes to accommodate the future connection of optic fibre technology
telecommunications.
60. Certification must be submitted to Council from all relevant service providers (Energex,
NBN and Unitywater which certifies that the development has met the requirements of
this Decision Notice and all applicable legislation at the time of construction.
Easements
61. Unless otherwise agreed in writing by the relevant service provider, any public or third
party infrastructure located on the subject site must be placed within an easement
registered against the title of the property.
62. All easements must be designed in accordance with the planning scheme and granted
at no cost to the Grantee. Where the Grantee is Council or a service authority, the
easement documentation must be in accordance with the Grantee’s standard easement
terms. Draft easement documentation must be submitted to Council for endorsement.
63. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
64. All excavation, fill, soil retaining structures and associated batters must be undertaken
in accordance with an Operational Works approval and contained entirely within the
subject site unless written permission from the respective landowner(s) is provided to
Council.
65. All retaining walls must be designed and constructed in accordance with the planning
scheme and must be certified by an RPEQ where exceeding 1.0m in height. All retaining
walls that are publicly accessible and exceed 1.0m in height must be fitted with a
commercial grade safety fence.
Page 9 of 53
Document Set ID: 23746767
Version: 6, Version Date: 22/05/2025
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewSearchable page text hides email addresses. Original files are unchanged and may show email addresses.