                      Water & Sewer Connections
               51.    An underground connection to reticulated water and sewerage must be provided to the
                      premises in accordance with the standards and requirements of Northern SEQ Distributor–
                      Retailer Authority (Unitywater).
               52.    A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater)
                      must be submitted to Council that certifies an underground connection to reticulated water
                      and sewerage has been provided to the premises.
                      ENGINEERING
                      Site Specific Conditions
               53.    The use of the existing fire trail located on Council land (Lot 1 SP239726) for purposes other
                      than maintenance and for emergency services (eg temporary access for construction
                      purposes) must be administered through an Access Permit by Council’s Parks and Gardens
                      department.
               54.    The emergency vehicle access located on Council land (Lot 1 SP239726) must be
                      constructed and maintained in accordance with the ‘Infrastructure Deed in Respect of
                      Construction of Access Track Crossing, Maintenance of Vegetation Buffer Zone And Access
                      Track (Including Crossing) For The Girraween Nature Refuge And The Aged Care Facility’
                      and a subsequent Operational Works permit.
               55.    The existing vegetation adjacent to the access must be pruned to improve driver sight lines
                      to both vehicles and pedestrians travelling in Cooyar Street and along the footpath. The
                      Australian Standard for Off-Street Car Parking (AS2890.1) must be used as a guide as with
                      Austroads Guide to Traffic Engineering Practice Part 5 Intersections at Grade and any
                      associated addendum.
               56.    All works associated with this permit must ensure that the fire trail is kept functional and
                      operational during all stages of work and for all intended uses (drainage outlet and access
                      for emergency services).
                      Car Parking
               57.    A minimum of 44 car parking spaces must be provided and marked on the site and made
                      available and accessible at all times while the use is open for business. The works must be
                      generally in accordance with Proposed Overall Ground Floor Plan (PD_A_003.1 E) dated 23
                      March 2023.
                      Stormwater Drainage
               58.    Stormwater runoff from the development must be connected to a lawful point of discharge
                      without causing scour or damage to the subject site or any adjoining properties. The works
                      must be undertaken in accordance with an Operational Works approval and be generally in
                      accordance with STP Consultants’ Stormwater Layout Plan (SKC01) dated 21 March 2023
                      and (SCK02) dated 20 March 2023. The works must include, but not be limited to:
                      a.      All Causeways (both temporary and permanent) must be constructed to comply with
                              all relevant sections of Queensland Urban Drainage Manual (QUDM);
                      b.      All Causeways (both temporary and permanent) must be constructed to comply with
                              Section 10.3.5 of Sunshine Coast Council’s Open Space Landscape Infrastructure
                              Manual 2022 (Type 5 Fire Access Trail); and
                      c.      Works must not adversely affect the existing water quality treatment capabilities of the
                              development as to result in pollutants exiting the site.
                      Easements
               59.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.


                                                                                                         Page 3 of 5

Document Set ID: 22389362
Version: 24, Version Date: 05/07/2023
Log in to download the original file

PLANNING & ENVIRONMENT REPORT - 132001 210127 3 - FINAL VERSION [As Published].pdf · 24.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.