environmental licen

 

Reasons for inclusion of development conditions

The Environmental Protection Agency is recognised as the assessment manager under the /ntegrated Planning
Amendment Regulation 1998 for coastal management.

The Activity for which this development approval is issued is simply a restatement of the activity as prescribed in
the legislation at the time of issuing this development approval. Where there is any conflict between the above
description of the Activity for which this development approval is issued and the conditions as specified in this
development approval as to the scale, intensity or manner of carrying out of the Activity, then such conditions
prevail to the extent of the inconsistency.

This development approval authorises the Activity. It does not authorise environmental harm unless a
concurrence agency condition within this development approval explicitly authorises that harm. Where there is
no condition, or the development approval is silent on a matter, the lack of a condition or silence shall not be
construed as authorising harm.

Referral agencies

Concurrence Agencies: Harbour Master, Brisbane Region, Maritime Safety Queensland
Advice Agencies: N/A
Referral Agencies: N/A

Additional comments or advice about the application

This approval does not remove the need to obtain any further approval for this development, which may be
required pursuant to this or other legislation, both State and Commonwealth. Applicants are advised to check
with all relevant statutory authorities for such approvals as may be required.

It is a requirement of the Environmental Protection Act 1994 that if the owner or occupier of this site becomes
aware a Notifiable Activity (as defined under Schedule 2 of the Environmental Protection Act 1994) is being
carried out on this land or that the land has been affected by a hazardous contaminant, they must, within thirty
(30) days after becoming aware the activity is being carried out, give notice to the Environmental Protection
Agency. A list of Notifiable Activities is provided within Schedule 2 of the Environmental Protection Act 1994.

In sourcing sand from the designated borrow area, Council should try to give preference to those areas covered
by existing leases or infrastructure.

Council is advised that for any works that result in the disturbance to marine plants, a relevant permit must be
obtained from the Department of Primary Industries and Fisheries. The dredging works will require an ERA19
licence under the Environmental Protection Act 1994.

Appeal rights

Section 4.1.27. of the Integrated Planning Act 1997 details your appeal rights regarding this decision.

 

' Permit includes licences, approvals, permits, authorisations, certificates, sanctions

or equivalent/similar as required by legislation administered by the

Environmental Protection Agency and the Queensland Parks and Wildlife Service

Environmental Protection Agency | Queensland Government

| Environmentat Protection Agency
www.epa.qid.gov.au aun a7 221 158 786 Queensland Parks and Wildlife Service

PAGE 20F 5
Log in to download the original file

11. Existing DA (2006).pdf · 3.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.