Capital Program 2024/2025 Delivery Status · Report
SERVICES & ORGANISATION COMMITTEE MEETING 6 MAY 2025
8.1 CAPITAL PROGRAM 2024/2025 DELIVERY STATUS
Author Director Infrastructure Services, Shaun Walsh
Infrastructure Services Department
Index ECM/ Subject/ 2024 - 2025 Annual Capital Works Program
Attachments 1. Capital Program Delivery Status
EXECUTIVE SUMMARY
• This report provides a status update for the Capital Works Program as at 31 March 2024,
and excludes disaster recovery projects.
• The approved capital budget provision for the 2024/25 financial year following Budget Review
2 is $46m, inclusive of carry forwards of $22.4m.
• Actual expenditure achieved to date is $20m (43.5% of budget) with $7.5m remaining in
commitments.
• There are currently 137 projects on the Capital Works Program in varying stages of delivery.
• Council has a current forecast of grant funding revenue of $11.7m with Council’s contribution
to these projects being $8.4m.
• The Planning and Design team are currently managing 24 Capital projects and are providing
planning and design services to over 60 projects in the 2024/25 financial year as well as
planning for the future Capital Works Program.
• The Infrastructure Planning Services team are currently supporting key master planning
initiatives with multiple sub-projects. The estimated value in 2024/25 is $1m with an estimated
future project investment value in the range of $75m+.
• Ongoing staffing constraints continue to impact service delivery. Recruitment is underway to
fill key positions with new initiatives for additional resourcing requested through the budget
approval process.
• Inclement weather, flooding, and cyclone preparations delayed projects however mitigation
efforts have reduced delays, with recovery works underway in outer regions.
• While budget limitations have influenced the pace of progress on project management
systems, internal improvements are underway, with a focus on making the most of available
resources.
• 2024/25 actual spend is tracking strongly, reflecting solid project delivery despite challenges
including staffing shortages, adverse weather, and budget constraints.
• Capital Works Planning for the 2025/26 financial year is well underway with 16 meetings held
to score and prioritise 80+ new initiates which have been workshopped at two Executive
Team meetings.
• A sizeable capital budget for the 2025/26 financial year will require innovative delivery
models. Timely approval would support improved planning and timely project
commencement.
RECOMMENDATION
That Council note the report by the Director Infrastructure Services to the Services & Organisation
Committee Meeting, 6 May 2025, providing an update on the delivery of the 2024/25 Capital Works
Program as at 31 March 2025.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 9 pages
Page 2
SERVICES & ORGANISATION COMMITTEE MEETING 6 MAY 2025
REPORT
This report is to inform Council of the overall status of the Capital Works Program, excluding disaster
recovery projects as at the end of March 2025, marking the end of the third quarter of the 2024/25
financial year.
The report provides key information relating to projects within the 2024/25 Capital Works Program
and confirms the delivery status of some projects undertaken during this quarter.
It is to be noted that the Financial Summary provided in this report is for project lifecycle progress
i.e. a major project funded over multiple years, and which commenced in an earlier financial year,
may be significantly further progressed than the 2024/25 financials indicate.
Current Financial Year Projects
The Capital Works Program consists of 137 projects in various stages of delivery.
Figure 1: Capital Works Program projects by stage of delivery
Major Projects
Major projects that have achieved substantial progress or reached significant milestones during Q3
of the 2024/25 financial year include:
• Noosaville, 90 Goodchap Street Office Fit Out – Reached completion
• Pomona, SES Amenities Upgrade - Reached completion
• Sunrise Beach, 56 Low Way Retaining Wall – Contract awarded
• Tewantin, Doonella Bridge Renewal – Design underway
• Sunshine Beach, Ed Webb Park Upgrade – Contract awarded
See Attachment 1 for photos of completed projects during Q3 of the 2024/25 financial year.
Page 3
SERVICES & ORGANISATION COMMITTEE MEETING 6 MAY 2025
Emergent Projects
Emergent projects approved by Project Control Group (PCG)/Capital Works Executive (CWE) during
Q3 2024/25 include:
• Peregian Beach, Playground, Planning & Design for Replacement
• Sunshine Beach, NAC Filtration System Preliminary Design
• Cooroy, Noosa Botanic Gardens CCTV Upgrade
• SEQ City Deal Public Art Initiative
• Cooroy, Butter Factory - Rectification of Height Safety Equipment
Tenders
Review of tenders for major projects during Q3 2024/25 include:
• Sunshine Beach, Ed Webb Park Upgrade
• Sunshine Beach, 56 David Low Way Retaining Wall
• Noosaville, 74 Goodchap Street Stormwater Drainage
• Shire Wide, Bus Stop Upgrades
• Noosa Heads, Noosa Main Beach Sea Wall Detailed Design
Upcoming tenders planned for Q4 2024/25 include:
• Cooroy Sports Complex, Gymnastics Upgrade & Multi-Purpose Area
• Doonan, Landfill, Cell 2.1 Eastern Batter Capping (Missing Link)
• Doonan, Noosaville/Eumundi Road Landfill Expansion of RRA
• Cooroy, Lake Macdonald Drive, Residential Subdivision
Major Programs 2024/25
The below summary provides an update on a selection of major programs within the 2024/25 Capital
Works Program.
Reseal Program
The Road Reseal Program has expended $4.2m of the $5.1m budget. The following roads on the
annual reseal program were undertaken during Q3 2024/25:
• Black Mountain, Blueberry Drive (Sugargum Place to Blueberry Loop & Roundabout to
Sugargum Place)
• Cooran, Railway Road (to Coles Creek Road)
• Cooroy, Kauri Street (Tewantin Road to Lake Macdonald Drive)
• Cootharaba, Cootharaba Road (from Louis Bazzo Drive to Road 30)
• Noosaville, Eenie Creek Road (Roundabout with Langura Street & from Hoffman Drive to
Commerce Court)
• Noosaville, Elizabeth Street (Roundabout at James Street)
• Noosaville, Eumundi Noosa Road (Beckmans Roundabout to Gateway Drive & Walter Hay
Drive Roundabout)
• Noosaville, James Street (Gympie Terrace to Elizabeth Street)
Page 4
SERVICES & ORGANISATION COMMITTEE MEETING 6 MAY 2025
• Peregian Beach, Oriole Avenue (from Landrail Street to #87)
• Pomona, Church Lane
• Pomona, Station Street (from Pine Street to end of school offset carpark)
• Sunrise Beach, Wollomia Way (Dame Patti Drive to #35)
• Tewantin, Griffith Avenue
• Tewantin, Maple Avenue
• Tewantin, Werin Street (Toolar Street to Gympie Street)
Heavy Patching Program
The Road Heavy Patching Program has expended $1.3m of the $1.5m to date. The following roads
received patching during Q3 2024/25:
• Black Mountain, Black Mountain Road
• Cooran, Bridge Street/Greenridge Pinbarren Road
• Cooran, Coles Creek Road
• Cooran, Tablelands Road
• Cooroibah, Lake Cooroibah Drive (from #3 to Jirrima Crescent)
• Cooroy, Belli Creek Road
• Cootharaba, Cootharaba Road (Louis Bazzo to Tomkinson and to new slip)
• Cootharaba, Cootharaba Road, (Junction Road to #208)
• Cootharaba, Cootharaba Road (edging)
• Federal, Middle Creek Road
• Kin Kin, Sister Tree Creek Road
• Kin Kin, Wahpunga Lane (Intersection to Jeremy’s Lane)
• Kin Kin, Williams Road
• Noosaville, Sea Eagle Drive State School Carpark
• Noosaville, Sternlight Street (Shorehaven Drive end)
• Noosaville, Wallace Park Carpark
• Pomona, Kylie Court
• Pomona, Signal Street
• Ridgewood, Cooroy Belli Creek Road (before Skyring Creek Road intersection)
Pathway Program
The Shire Wide Pathway Program continued into Q3 of the 2024/25 financial year. The following
pathway renewals that are currently being delivered (constructed) during this quarter include:
• Noosa Heads, Seagull Park
• Shire Wide - Pathway Renewal Program:
o Noosa Heads, Alex Dan Park
o Noosaville, Gympie Terrace
Page 5
SERVICES & ORGANISATION COMMITTEE MEETING 6 MAY 2025
o Tewantin, Moorindil Street
The following pathways are in the planning, design and procurement stages, in preparation for
construction commencement during Q4 2024/25:
• Pomona, Summit Road
• Shire Wide - Pathway Renewal Program
o Cooran, Bridge Street
o Cooroy, Diamond Street
o Noosa Heads, Noosa Parade
o Noosaville, Gympie Terrace
o Tewantin, Sheild Street/Werin Street
o Tewantin, Waratah Close
o Tewantin, Yellowwood Drive/McKinnon Drive
Noosa Biosphere Trails
Upgrade works on the Noosa Biosphere Trails have continued through Q3 of 2024/25, with the
completion of the following projects:
Works are still ongoing on:
• Twin Hills, Wahpunga Trail – disaster landslip works including drainage, new signage, new
fencing, new shade structure and new vegetation. Expected completion Q4. In line with
funding grant.
Planning is ongoing on the following trails:
• Boreen Point to Tewantin, Cooroibah Trail
• Lake McDonald to Peregian Beach, New Weyba Trail
• Pomona to Cooroy, Kurui Trail – Renewal
• Cooran to Kin Kin, Woondum Trail and Kin Kin to Lake Macdonald Wahpunga Trail -
Renewal
Page 6
SERVICES & ORGANISATION COMMITTEE MEETING 6 MAY 2025 Link to Corporate Plan Theme No. 2. - Liveability Liveability encompasses housing, facilities and services, transport, health and wellbeing to enable an inclusive, connected and vibrant community. Objective 2.7 Fund and deliver sustainable assets and facilities and associated services responding to the changing needs of the community and the challenges and opportunities of the future. Previous Council Consideration Nil.
Page 7
SERVICES & ORGANISATION COMMITTEE MEETING 6 MAY 2025 Finance The year-to-date capital delivery expenditure as at 31 March 2025 is approximately $20m or 43% of the $46m approved Capital Works Program budget (BR2). Table 1 below demonstrates the approved budget, actual expenditure, remaining commitments and forecast spend for the 2024/25 financial year. Figure 2 below demonstrates actual expenditure to date plus the forecast expenditure as at the end of Q3. CWP Budget 2024/25 Approved Budget $46,040,296 Actuals Year to Date $19,981,731 Remaining Commitments/contract values $7,467,259 Forecast Spend for 2024/25 Financial Year (includes Actuals FYTD) $32,939,800 Table 1 – Capital Finance data as at 31 March 2025 Figure 2 – Actuals (FYTD) + Forecast as at 31 March 2025
Page 8
SERVICES & ORGANISATION COMMITTEE MEETING 6 MAY 2025
Grant Funding
The 2024/25 financial year Capital Works Program includes an unprecedented amount of grant
funding.
Figures 3 and 4 below demonstrate the non-grant funded capital projects compared to projects with
grant funding, as well as Council’s contribution towards grant funded projects.
Figure 3 detail Percentage of CWP Value of CWP
Non-Grant funded Projects 56% $25.8m
Projects with Grant Funding 44% $20.2m
Figure 3 – Projects with and without grant funding.
Percentage of
Figure 4 detail Value of CWP
CWP
Non-Grant funded Projects 56% $25.8m
Grant funding revenue 26% $11.7m
Councils’ contribution to projects with grant funding 18% $8.4m
Figure 4 – Projects by funding source
Page 9
SERVICES & ORGANISATION COMMITTEE MEETING 6 MAY 2025
Risk & Opportunities
Q3 has presented several challenges and opportunities for Council. Despite facing constraints such
as staff shortages, inclement weather, and budget limitations, there has been significant progress in
various areas. Below are the key highlights:
• Staff shortages continue to constrain delivery ability. Recruitment processes are in progress, but
more resources are needed for optimal delivery.
• Inclement weather, flooding, and cyclone preparations hampered project delivery. Mitigation
planning and measures helped overcome most delays, with outer shire regions now focusing on
flood-related repairs.
• Budget limitations have influenced the pace at which project management systems and
supporting software can be developed and implemented. Despite these constraints, internal
teams have focused on making incremental improvements using existing resources. These
efforts reflect a strong commitment to enhancing project oversight and efficiency within current
financial parameters. While progress has been steady, additional investment would enable more
comprehensive and timely enhancements moving forward.
• The 2024/25 financial year is expected to result in a strong actual spend, which is a positive
outcome given the range of challenges faced. Despite pressures of staffing shortages, adverse
weather, and budget constraints, Council has maintained solid project delivery and investment
performance.
• Capital Works Planning for the 2025/26 financial year is well underway with 16 meetings held to
score and prioritise 80+ new initiates which have been workshopped at two Executive Team
Meetings.
• A sizeable capital budget for 2025/26 financial year will require innovative delivery models.
Timely approval would benefit planning and project commencement.
Human Rights
Human Rights Compatibility Statement
In developing this Report, the subject matter has been considered in accordance with the
requirements of the Queensland Human Rights Act 2019. It is considered that the subject matter
does not conflict with any human rights and supports a human rights approach to decision making
by Council. Council representatives will endeavour to act and make decisions under this report in a
manner that is compatible with human rights. This report should be read in conjunction with
Council’s Human Rights Policy.
Consultation
External Consultation - Community & Stakeholder
Nil
Page 10
SERVICES & ORGANISATION COMMITTEE MEETING 6 MAY 2025
Internal Consultation
Departments consulted:
Office of the CEO, Mayor & Community Services Corporate Services
Councillors
Mayor & Councillors Director Director
Chief Executive Officer Community Development x Financial Services
Executive Officers x Sport & Active Lifestyles Fleet
Community Engagement x Arts & Culture Revenue Services
People & Culture Community Connection ICT
Governance Customer Experience Procurement
Commercial Property
Strategy & Environment Development & Regulation Infrastructure Services
Director Director x Director
Strategy & Sustainability Development Assessment x Infrastructure Planning, Design
and Delivery
Economic Development & Local Laws x Civil and Asset operations
Destination Management
Environmental Services Environmental Health x Waste
Innovation & Digital Hub Building & Plumbing x Building & Facilities
Property / Permits Disaster Management
Used in these records
Capital Program 2024/2025 Delivery Status · ReportReportsMeeting 773 · read item & discussion ↗
About this file
- File size
- 1.1 MB (small file)
- File type
No other editions are linked here.